Project 19AI0391
DPWH infrastructure contract
Contract ID:
19AI0391
Fingerprint:
7e6d13278d1868…ca22f91ec1 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 6, 2019 (6 yrs 11 mo ago) · Target/actual end Feb 3, 2020
Description:
CONCRETING OF BRGY. STA. MARIA FMR, BRGY. STA. MARIA, UMINGAN, PANGASINAN
Category:
Roads
Implementing office:
DPWH Pangasinan 3rd DEO · Region I
Contractor:
R.G. TABIN CONSTRUCTION & SUPPLY · DPWH contractor code 26830
As listed: R.G.TABIN CONSTRUCTION AND SUPPLY
Contract amount:
₱4,726,352.14 (₱4.7M)
Funding source:
Outside Infra - GAA 2019 DA FMR
Budget year:
2019
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 83ffa3891254… | Nov 28, 2019 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PANGASINAN 3RD DEO | ₱4,726,352.14 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25AI0187 | Jul 18, 2025 | REHABILITATION OF ROAD, PHASE 1, UMINGAN, PANGASINAN | On-Going | ₱117.0M |
| 25AI0188 | Jul 18, 2025 | REHABILITATION OF ROAD, PHASE 2, UMINGAN, PANGASINAN | On-Going | ₱117.0M |
| 25A00478 | Jul 4, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION / REHABILITATION OF ROADS, UMINGAN, PANGASINAN, PHASE 3 | On-Going | ₱16.3M |
| 25AI0203 | May 29, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG BANILA AND ALLIED RIVERS, UMINGAN, PANGASINAN (PACKAGE 3) | Completed | ₱48.7M |
| 25AI0204 | May 29, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG BANILA AND ALLIED RIVERS, UMINGAN, PANGASINAN (PACKAGE 4) | Completed | ₱48.7M |
| 25AI0205 | May 29, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG BANILA AND ALLIED RIVERS, UMINGAN, PANGASINAN (PACKAGE 5) | Completed | ₱48.7M |
| 25AI0206 | May 29, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG BANILA AND ALLIED RIVERS, UMINGAN, PANGASINAN (PACKAGE 6) | Completed | ₱48.7M |
| 25A00268 | Apr 7, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF ROAD, TAYUG, PANGASINAN | On-Going | ₱19.2M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.