Completed
Physical progress:
100%
Timeline:
Start Jun 10, 2019 (7 yrs 5 mo ago) · Target/actual end Sep 7, 2019
Description:
REPAIR/REHABILITATION OF MULTI-PURPOSE BUILDING, ZONE II, PUROK 8 NEIGHBORHOOD ASSOCIATION, BRGY. MAHABANG PARANG, ANGONO, RIZAL
Category:
Buildings and Facilities
Implementing office:
DPWH Rizal 1st DEO · Region IV-A
Contractor:
FLAG CONSTRUCTION CORPORATION(FOR. FLAG CONSTRUCTI · DPWH contractor code 21758
Contract amount:
₱2,821,018.61 (₱2.8M)
Funding source:
Regular Infra - GAA 2019 LP
Budget year:
2019
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DN0085 | May 28, 2025 | REHABILITATION OF ROAD, BARANGAY KALAYAAN, ANGONO, RIZAL (FIRST DISTRICT) | On-Going | ₱9.6M |
| 25DN0086 | May 28, 2025 | CONSTRUCTION OF ROAD, DOÑA AURORA STREET, BARANGAY POBLACION IBABA, ANGONO, RIZAL (FIRST DISTRICT) | On-Going | ₱9.9M |
| 25DN0049 | Apr 8, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, ANGONO RIVER, BARANGAY SAN VICENTE, ANGONO, RIZAL (FIRST DISTRICT) | Completed | ₱49.0M |
| 25DN0046 | Apr 7, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BANGIAD CREEK, TAYTAY, RIZAL (FIRST DISTRICT) | On-Going | ₱18.8M |
| 24DN0146 | Jul 29, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (ANGONO ART CENTER WITHIN THE ANGONO LAKESIDE ECOPARK), BARANGAY SAN VICENTE ANGONO, RIZAL (FIRST DISTRICT) | On-Going | ₱9.6M |
| 24D00242 | Jul 19, 2024 | CONSTRUCTION OF DRAINAGE ALONG LAKESHORE, BARANGAY KALAYAAN, ANGONO, RIZAL | On-Going | ₱56.6M |
| 24DN0168 | Jul 15, 2024 | IMPROVEMENT OF ROAD AND DRAINAGE SYSTEM, IBAÑEZ ST., BARANGAY SAN ISIDRO, BARANGAY STO. NIÑO AND BARANGAY SAN VICENTE ANGONO, RIZAL (FIRST DISTRICT) | On-Going | ₱68.5M |
| 24DN0145 | Jun 25, 2024 | CONSTRUCTION OF DRAINAGE SYSTEM, FLORENTINO ST., BRGY. KALAYAAN ANGONO, RIZAL (FIRST DISTRICT) | Completed | ₱7.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.