Project 19DO0032
DPWH infrastructure contract
Contract ID:
19DO0032
Fingerprint:
abeffd8ee721bc…2592517084 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 18, 2019 (7 yrs 3 mo ago) · Target/actual end Jan 17, 2020
Description:
OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE - WIDENING OF PERMANENT BRIDGES - BARAS BR. (B02855LZ) ALONG SAGBAT - PILILLA DIV. RD. BARAS, RIZAL
Category:
Bridges
Implementing office:
DPWH Rizal 2nd DEO · Region IV-A
Contractor:
M.J. BEVANT CORP. · DPWH contractor code 36298
Contract amount:
₱29,400,000.00 (₱29.4M)
Funding source:
Regular Infra - GAA 2019 OO-1
Budget year:
2019
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 4139be822b40… | Jun 28, 2019 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - RIZAL II DEO | ₱28,340,906.44 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DO0010 | Jun 5, 2025 | ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BARAS RIVER, PHASE 3, BA | On-Going | ₱48.3M |
| 25DO0011 | Jun 5, 2025 | ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BARAS RIVER, PHASE 5, BA | On-Going | ₱48.3M |
| 25DO0042 | Feb 24, 2025 | NATIONAL BUILDING PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES - CONSTRUCTION OF DPWH OFFICE BUILDING OF RIZAL 2ND DEO, BARAS, RIZAL | Completed | ₱100.1M |
| 25DO0013 | Feb 13, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BARANGAY SANTIAGO, | Completed | ₱48.8M |
| 25DO0041 | Feb 13, 2025 | NATIONAL BUILDING PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES - CONSTRUCTION OF DPWH RIZAL 2ND DISTRICT ENGINEERING OFFICE, BARAS, RIZAL | Completed | ₱49.0M |
| 24D00283 | Oct 21, 2024 | CONSTRUCTION OF NEW SUPER HEALTH CENTERS / RHU BARAS SUPER HEALTH CENTER, RIZAL | On-Going | ₱11.7M |
| 24DO0080 | Mar 25, 2024 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF DRAINAGE ALONG SAGBAT-PILILLA DIVERSION ROAD K005 | Completed | ₱49.0M |
| 24DO0011 | Feb 7, 2024 | ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG BARAS RIVER, BARANGAY SAN JOSE, BARAS, RIZAL | Completed | ₱91.7M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.