Project 19EH0016
DPWH infrastructure contract
Contract ID:
19EH0016
Fingerprint:
047f13ee6cdd77…ee206c4c21 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 3, 2019 (7 yrs 4 mo ago) · Target/actual end Sep 4, 2019
Description:
RETROFITTING/STRENGTHENING OF PERMANENT BRIDGE - BONLAO BR. (B00003TL) ALONG TABLAS CIRCUMFERENTIAL ROAD, K0087 + 873 - K0087 + 892, TABLAS ISLAND, ROMBLON
Category:
GAA 2019 OO-1
Implementing office:
DPWH Romblon DEO · MIMAROPA Region
Contractor:
ULTIMATE BUILDER'S & CONST. SUPPLY · DPWH contractor code 39221
Location:
Contract amount:
₱6,749,004.37 (₱6.7M)
Funding source:
Regular Infra - GAA 2019 OO-1
Budget year:
2019
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25EH0154 | May 27, 2025 | CONSTRUCTION OF ROAD, BARANGAY LAWAN TO BARANGAY SAN ISIDRO (PHASE 2), ALCANTARA, ROMBLON | On-Going | ₱93.5M |
| 25EH0161 | May 27, 2025 | CONSTRUCTION OF ROAD, SITIO MAGSUPOT TO SITIO ILAYA, BARANGAY CALAGONSAO, ALCANTARA, ROMBLON | On-Going | ₱140.2M |
| 25EH0116 | May 23, 2025 | CONSTRUCTION OF CAMILI- RNIT ACCESS ROAD, ALCANTARA, ROMBLON | On-Going | ₱11.6M |
| 25EH0088 | May 21, 2025 | CONSTRUCTION OF ROAD, ALCANTARA TO ODIONGAN, ALCANTARA, ROMBLON | On-Going | ₱142.7M |
| 25EH0003 | Mar 28, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), ALCANTARA NATIONAL HIGH SCHOOL, ALCANTARA, ROMBLON | Completed | ₱4.9M |
| 25EH0006 | Mar 24, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), ROMBLON NATIONAL INSTITUTE OF TECHNOLOGY - RNIT, PHASE I, BARANGAY POBLACION, ALCANTARA, ROMBLON | Completed | ₱5.9M |
| 25EH0037 | Mar 24, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), ALCANTARA NATIONAL HIGH SCHOOL, SENIOR HIGH SCHOOL, ALCANTARA, ROMBLON | Completed | ₱4.9M |
| 25E00141 | Mar 12, 2025 | ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC P[UBLIC BUILDINGS/FACILITIES- CONST. OF COASTAL ROAD, BRGY. CALAGONSAO, ALCANTARA, ROMBLON | On-Going | ₱276.2M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.