Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 19GG0022

DPWH infrastructure contract
Contract ID:
19GG0022
Fingerprint:
c3cb3ba7c70d96…86849d3ffa Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 11, 2019 (7 yrs 4 mo ago) · Target/actual end Dec 20, 2019
Description:
RECONSTRUCTION TO CONCRETE PAVEMENT OF MANDURRIAO - SAN MIGUEL - ALIMODIAN - MAASIN - CABATUAN ROAD, K0033 + 734 - K0034 + 445
Category:
Roads
Implementing office:
DPWH Iloilo 2nd DEO · Region VI
Contractor:
EARLY RISER CONSTRUCTION · DPWH contractor code 33960
Contract amount:
₱10,322,399.91 (₱10.3M)
Funding source:
Regular Infra - GAA 2019 OO-1
Budget year:
2019

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GR0019Jul 7, 2025CONSTRUCTION OF FLOOD CONTROL/SLOPE PROTECTION ALONG TIGUM RIVER, MAASIN ILOILOOn-Going₱39.1M
25GG0062Jul 4, 2025CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY CANAWILI, MAASIN, ILOILOCompleted₱3.5M
25GG0063Jul 4, 2025CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY UBIAN, MAASIN, ILOILOCompleted₱3.9M
25GG0100Jul 4, 2025CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY MAGSAYSAY, MAASIN, ILOILOOn-Going₱2.7M
25GG0146Jul 4, 2025CONSTRUCTION OF ROAD, BARANGAY BULAY, MAASIN, ILOILOCompleted₱4.9M
25GG0152Jul 4, 2025CONSTRUCTION OF MULTI - PURPOSE BUILDING, MAASIN, ILOILOOn-Going₱9.9M
25GG0019Jul 3, 2025CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY DALUSAN, MAASIN, ILOILOCompleted₱3.5M
25GG0020Jul 3, 2025CONSTRUCTION (COMPLETION) OF MULTI - PURPOSE BUILDING, BARANGAY SINUBSUBAN, MAASIN, ILOILOCompleted₱2.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.