Project 19IE0079

DPWH infrastructure contract
Contract ID:
19IE0079
Fingerprint:
f32712765d0516…dd96dee4bd Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 10, 2019 (7 yrs 4 mo ago) · Target/actual end Aug 19, 2019
Description:
CONSTRUCTION OF FLOOD CONTROL, BARANGAY KOKOY ROMUALDEZ,CALUBIAN, LEYTE
Category:
Flood Control and Drainage
Implementing office:
DPWH Leyte 3rd DEO · Region VIII
Contractor:
WAWOT BUILDERS · DPWH contractor code 33592
Contract amount:
₱2,867,242.35 (₱2.9M)
Funding source:
Regular Infra - GAA 2019 LP
Budget year:
2019

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
ba96cb5ed4b4…Jun 28, 2019DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LEYTE 3RD DEO₱2,867,242.35

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25IE0082Aug 24, 2025CONSTRUCTION OF BRIDGE, BARANGAY VILLAHERMOSA, CALUBIAN, LEYTEOn-Going₱39.2M
25IE0099Aug 4, 2025CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS), CALUBIAN NATIONAL HIGH SCHOOL-VILLALON ANNEX, CALUBIAN, LEYTECompleted₱322.4K
25IE0088Jul 17, 2025CONSTRUCTION OF TIDE PROTECTION EMBANKMENT, BARANGAY OBISPO, CALUBIAN, LEYTEOn-Going₱72.9M
25IE0089Jul 10, 2025CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG CALUBIAN-JUBAY ROAD, CALUBIAN, LEYTEOn-Going₱72.4M
25IE0084Jun 5, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) BARANGAY OBISPO, CALUBIAN, LEYTEOn-Going₱4.9M
25IE0085Jun 5, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY HALL, BARANGAY TABLA, CALUBIAN, LEYTEOn-Going₱4.9M
25IE0059May 29, 2025CONCRETING OF BRGY. VILLAHERMOSA TO BRGY. GARRIDO FMR, BRGY. VILLAHERMOSA AND BRGY. GARRIDO, CALUBIAN, LEYTEOn-Going₱14.9M
25IE0066May 26, 2025CONSTRUCTION OF BRIDGE, BARANGAY CABRADILLA, CALUBIAN, LEYTEOn-Going₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.