Project 19KG0028

DPWH infrastructure contract
Contract ID:
19KG0028
Fingerprint:
067a770995054d…56942c3e3b Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 19, 2019 (7 yrs 3 mo ago) · Target/actual end Sep 16, 2019
Description:
CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-TERTIARY ROADS,LANAO DEL NORTE INTERIOR CIRCUMFERENTIAL (LDNICR), K1547+308-K1548+040,K1548+170,BALOI,LANAO DEL NORTE
Category:
Roads
Implementing office:
Contractor:
AL-HAYAT CONSTRUCTION · DPWH contractor code 44954
Contract amount:
₱1,187,361.16 (₱1.2M)
Funding source:
Regular Infra - GAA 2019 OO-1
Budget year:
2019

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25KG0063May 20, 2026LAST MILE SCHOOL PROGRAM-BUBONG PACO PS, BALOI, LANAO DEL NORTEOn-Going₱20.0M
25KG0056Nov 20, 2025LGU HOSPITAL, BALO-I PROVINCIAL HOSPITAL, LANAO DEL NORTEOn-Going₱29.5M
25KG0044Jun 17, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (PUBLIC MARKET), BRGY. POBLACION WEST, BALOI, LANAO DEL NORTECompleted₱49.0M
25KG0045Jun 17, 2025CONSTRUCTION OF LEVEL III BARANGAY WATER SUPPLY SYSTEM (DEEP WELL), MARIA CRISTINA, BALOI, LANAO DEL NORTECompleted₱9.7M
25KG0013Feb 19, 2025REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG ILIGAN CITY-MARAWI RD-K1544+000-K1545+903, K1546+413-K1546+932Completed₱64.1M
25KG0019Jan 21, 2025CONSTRUCTION OF PROTECTION DIKE, BALUT CIS, BALO-I, LANAO DEL NORTECompleted₱14.5M
25KG0030Jan 21, 2025CONSTRUCTION (COMPLETION) OF BALOI WATER SUPPLY SYSTEM (PHASE II), BARANGAY POBLACION, BALO-I, LANAO DEL NORTECompleted₱14.5M
24KG0035May 20, 2024REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS ALONG ILIGAN CITY-MARAWI CITY RD. K1536+(-635)-K1536+500, K1545+312-K1546+000, K1553+665-K1554+207, K1554+281-K1554+331On-Going₱71.7M