Project 19ME0040
DPWH infrastructure contract
Contract ID:
19ME0040
Fingerprint:
23ba3f4455630b…f705559705 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 7, 2019 (7 yrs 4 mo ago) · Target/actual end Mar 30, 2021
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING (SLAUGHTER HOUSE), BRGY. POBLACION; MAITUM, SARANGANI PROVINCE.
Category:
Buildings and Facilities
Implementing office:
DPWH Sarangani DEO · Region XII
Contractor:
ESCORR BUILDERS AND TRADERS INC. · DPWH contractor code 43230
As listed: ESCORR BUILDERS AND TRADERS, INC.
Contract amount:
₱2,970,000.00 (₱3.0M)
Funding source:
Regular Infra - GAA 2019 LP
Budget year:
2019
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| ce11bd9dafea… | May 31, 2019 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS SARANGANI DISTRICT E | ₱2,803,995.29 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25ME0112 | Aug 15, 2025 | CONSTRUCTION OF MALALAG MULTI-PURPOSE BUILDING, MALALAG, MAITUM, SARANGANI PROVINCE | Completed | ₱7.9M |
| 25ME0082 | Jul 30, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BUILDING NO.1, BARANGAY MALALAG, MAITUM, SARANGANI PROVINCE | Completed | ₱15.8M |
| 25ME0083 | Jul 30, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BUILDING NO. 2, BARANGAY MALALAG, MAITUM, SARANGANI PROVINCE | Completed | ₱29.7M |
| 25ME0099 | Jul 30, 2025 | CONSTRUCTION OF MAGULING MULTI-PURPOSE BUILDING, MAGULING, MAITUM, SARANGANI PROVINCE | Completed | ₱5.9M |
| 25ME0100 | Jul 30, 2025 | CONSTRUCTION OF MABAY MULTI-PURPOSE BUILDING, MAITUM, SARANGANI PROVINCE | Completed | ₱5.9M |
| 25ME0105 | Jul 30, 2025 | CONSTRUCTION OF BATIAN MULTI-PURPOSE BUILDING (BARANGAY HALL), BATIAN, MAITUM, SARANGANI PROVINCE | Completed | ₱5.9M |
| 25ME0008 | Jun 13, 2025 | NRJ MALALAG LEADING TO BARANGAY KIAYAP ROAD LEADING TO KIAYAP FALLS, MAITUM, SARANGANI PROVINCE | Terminated | ₱0 |
| 25ME0048 | Mar 31, 2025 | CONSTRUCTION OF KALAONG RIVER CONTROL, MAITUM, SARANGANI PROVINCE | Completed | ₱82.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.