Project 19N00147
DPWH infrastructure contract
Contract ID:
19N00147
Fingerprint:
63621b900a69a8…5995b30559 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jan 23, 2020 (6 yrs 9 mo ago) · Target/actual end Apr 11, 2020
Description:
CONSTRUCTION OF RAIN WATER COLLECTION SYSTEM 2019, BUTUAN CITY, AGUSAN DEL NORTE
Category:
Water Provision and Storage
Implementing office:
DPWH Region XIII · Region XIII
Contractor:
JQG BUILDERS · DPWH contractor code 36042
Contract amount:
₱3,518,329.55 (₱3.5M)
Funding source:
Regular Infra - GAA 2019 CSSP
Budget year:
2019
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 23d1b80dcb53… | Dec 3, 2019 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CARAGA | ₱3,418,283.69 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25ND0027 | Aug 7, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING (COVERED COURT WITH BLEACHERS), BARANGAY LAWAN-LAWAN, LAS NIEVES, AGUSAN DEL NORTE | Completed | ₱6.9M |
| 25ND0131 | Aug 7, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY TINUCORAN, LAS NIEVES, AGUSAN DEL NORTE | Completed | ₱6.8M |
| 25ND0071 | Jul 18, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING AT LAS NIEVES NATIONAL HIGH SCHOOL BARANGAY POBLACION, LAS NIEVES, AGUSAN DEL NORTE | On-Going | ₱9.9M |
| 25N00099 | Apr 10, 2025 | AGUSAN DEL NORTE/AGUSAN DEL SUR NORTH-SOUTH LATERAL ROAD, (LAS NIEVES, AGUSAN DEL NORTE - KAPALONG, DAVAO DEL NORTE), LAS NIEVES | On-Going | ₱48.1M |
| 25N00259 | Apr 8, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG AGUSAN RIVER BASIN, PACKAGE 3, BARANGAY POBLACION, LAS NIEVES, AGUSAN DEL NORTE | On-Going | ₱149.3M |
| 25N00260 | Apr 8, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG AGUSAN RIVER BASIN, PACKAGE 4, PROTECTING BARANGAY POBLACION, LAS NIEVES, AGUSAN DEL NORTE | On-Going | ₱149.3M |
| 25N00155 | Mar 28, 2025 | LAS NIEVES BRIDGE ALONG NRJ AGUSAN-MALAYBALAY ROAD-BRGY. AMBACON-BRGY. MALICATO-NRJ DAANG MAHARLIKA, PHASE 8, AGUSAN DEL NORTE | On-Going | ₱93.6M |
| 25N00220 | Mar 28, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG AGUSAN RIVER (AMBACON-PINANA-AN SECTION) DOWNSTREAM, PHASE 3, LAS NIEVES, AGUSAN DEL NORTE | On-Going | ₱95.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.