Physical progress:
83.2%
Timeline:
Start Jul 21, 2022 (4 yrs 3 mo ago)
Description:
PR-01A, GUTALAC-BALIGUIAN ALTERNATIVE ROAD, ZAMBOANGA DEL NORTE, K2027+802.62-K2055+764.93 (WITH EXCEPTIONS) UNDER ADB LOAN 3631-PHI: IMPROVING GROWTH CORRIDORS IN MINDANAO ROAD SECTOR PROJECT (IGCMRSP)
Category:
Bridges: Construction - Concrete (Superstructure) - with Cast-in-Place Piles, Roads: Construction - PCCP
Implementing office:
DPWH Roads Management Cluster II (Multilateral) · Central Office
Contractor:
Contract amount:
₱1,064,377,226.90 (₱1.06B)
Funding source:
Regular Infra - Bridges: Construction - Concrete (Superstructure) - with Cast-in-Place Piles, Roads: Construction - PCCP
Budget year:
2021
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25JJ0047 | Apr 4, 2025 | CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM (RWCS) AT (1) KAUSWAGAN ELEMENTARY SCHOOL, BALIGUIAN, ZN (2) BALIGUIAN CENTRAL SCHOOL, BALIGUIAN, ZN (3) S. CABRAL ELEMENTARY SCHOOL, SIOCON, ZN (4) SIBUCO CENTRAL SCHOOL, SIBUCO, ZN (5) SIRAWAI CENTRAL SCHOOL, | On-Going | ₱2.6M |
| 25JJ0004 | Mar 27, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, LILOY-SIOCON RD - K2064 + 728 - K2064 + 757, K2064 + 939 - K2064 + 972 | Completed | ₱13.4M |
| 25JJ0008 | Mar 27, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, LILOY-SIOCON RD - K2056 + 892 - K2056 + 942 | Completed | ₱24.7M |
| 25JJ0009 | Mar 27, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, LILOY-SIOCON RD - K2028 + 110 - K2028 + 124, K2029 + 560 - K2029 + 620, K2030 + 013 - K2030 + 043, K2030 + 452 - K2030 + 494, K2030 + 527 - K2030 + 552 | Completed | ₱38.0M |
| 25JJ0010 | Mar 27, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, LILOY-SIOCON RD - K2031 + 208 - K2031 + 235, K2031 + 847 - K2031 + 882 | Completed | ₱16.4M |
| 25JJ0016 | Mar 27, 2025 | PAVING OF UNPAVED ROADS - SECONDARY ROADS, LILOY-SIOCON RD - K2049 + 500 - K2051 + 800 | Completed | ₱76.7M |
| 25JJ0018 | Mar 27, 2025 | PAVING OF UNPAVED ROADS - SECONDARY ROADS, LILOY-SIOCON RD - K2040 + 250 - K2040 + 896 | On-Going | ₱21.9M |
| 25JJ0019 | Mar 27, 2025 | PAVING OF UNPAVED ROADS - SECONDARY ROADS, LILOY-SIOCON RD - K2053 + 600 - K2054 + 300 | On-Going | ₱24.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.