Project 20AC0040
DPWH infrastructure contract
Contract ID:
20AC0040
Fingerprint:
4ad96f8916e749…2258b8a5df Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 8, 2020 (6 yrs 5 mo ago) · Target/actual end Nov 4, 2020
Description:
CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY CAPANGDANAN, BANTAY, ILOCOS SUR
Category:
Buildings and Facilities
Implementing office:
DPWH Ilocos Sur 1st DEO · Region I
Contractor:
MAPLE LEAF ENGINEERING AND CONSTRUCTION · DPWH contractor code 41235
Contract amount:
₱5,445,000.00 (₱5.4M)
Funding source:
Regular Infra - GAA 2020 LP
Budget year:
2020
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| d4f0eb414ff4… | May 21, 2020 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ILOCOS SUR 1ST DEO | ₱5,332,335.79 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25AC0091 | Jul 13, 2026 | CONSTRUCTION OF CLASSROOMS, BANTAY WEST IS, BANTAY, ILOCOS SUR | On-Going | ₱12.2M |
| 25AC0073 | Jun 15, 2026 | CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING (TOURIST CENTER), BANTAY, ILOCOS SUR | On-Going | ₱144.2M |
| 25AC0033 | Jul 11, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ABRA RIVER, BANTAY, ILOCOS SUR | Completed | ₱47.5M |
| 25AC0077 | Jul 10, 2025 | PREVENTIVE MAINTENANCE - PRIMARY ROADS MANILA NORTH RD - K0397+205 - K0398+925 | On-Going | ₱46.8M |
| 25AC0029 | Jun 27, 2025 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES, PAING BR. 2 (B04627LZ) ALONG MANILA NORTH RD | Completed | ₱8.4M |
| 25AC0038 | Jun 5, 2025 | CONSTRUCTION OF ROAD, BARANGAY SAGPAT, BANTAY, ILOCOS SUR | Completed | ₱5.8M |
| 25AC0064 | Jun 2, 2025 | CONSTRUCTION OF ROAD, BARANGAY TAGUIPORO TO BARANGAY RAOIS, BANTAY, ILOCOS SUR | On-Going | ₱19.2M |
| 25AC0006 | Apr 11, 2025 | CONSTRUCTION OF SPUR DIKE AT BANAOANG PIS, BANTAY, ILOCOS SUR | Completed | ₱14.1M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.