Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 20DN0063

DPWH infrastructure contract
Contract ID:
20DN0063
Fingerprint:
1b298c2368d602…b5705ef17a Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 7, 2020 (5 yrs 11 mo ago) · Target/actual end Jul 4, 2021
Description:
IMPROVEMENT / CONSTRUCTION OF FLOOD CONTROL STRUCTURES OF CAINTA RIVER, BRGY. SAN JUAN CAINTA, RIZAL
Category:
Flood Control and Drainage
Implementing office:
DPWH Rizal 1st DEO · Region IV-A
Contractor:
Contract amount:
₱29,512,156.34 (₱29.5M)
Funding source:
Regular Infra - GAA 2020 OO-2
Budget year:
2020

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25DN0108May 29, 2025REHABILITATION OF DRAINAGE ALONG PAROLA STREET, BARANGAY SAN ANDRES CAINTA, RIZAL (FIRST DISTRICT)On-Going₱9.9M
25DN0074May 27, 2025REHABILITATION OF ROAD, BARANGAY MAMBUGAN AND BARANGAY MUNTINDILAW, ANTIPOLO CITY, RIZAL (FIRST DISTRICT)On-Going₱14.4M
25DN0078May 27, 2025REHABILITATION OF ROAD, PHASE 2, BARANGAY MAYAMOT, ANTIPOLO CITY, RIZAL (FIRST DISTRICT)On-Going₱9.6M
25DN0015May 23, 2025ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - CAINTA - KAYTICKLING - ANTIPOLO - TERESA - MORONG RD - K0020+402 - K0020+594, K0020+800 - K0019+222, RIZAL (FIRST DISTRICT)Completed₱14.1M
25DN0023May 23, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE, HALANG CREEK, PHASE 4, BARANGAY MAYAMOT, ANTIPOLO CITY, RIZAL (FIRST DISTRICT)On-Going₱69.6M
25OB0450May 22, 2025REHABILITATION OF FLOOD MITIGATION STRUCTURE ALONG ILUGIN CREEK, PASIG CITY (PHASE 1)Completed₱47.3M
25D00064May 21, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BALANTI CREEK, CAINTA, RIZALOn-Going₱95.0M
25D00084May 21, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE, CAINTA RIVER, BARANGAY SAN JUAN, CAINTA, RIZALOn-Going₱94.1M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.