Project 20FG0103
DPWH infrastructure contract
Contract ID:
20FG0103
Fingerprint:
d28b22ebf73c79…442038c688 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 6, 2020 (6 yrs 1 mo ago) · Target/actual end Dec 19, 2021
Description:
CONCRETING OF BARANGAY BAHI TO BARANGAY SAGRADA FARM TO MARKET ROAD (FMR) BARANGAY BAHI AND BARANGAY SAGRADA, GARCHITORENA, CAMARINES SUR
Category:
Roads
Implementing office:
DPWH Camarines Sur 4th DEO · Region V
Contractor:
S & RV CONSTRUCTION & SUPPLY · DPWH contractor code 19203
Contract amount:
₱12,435,656.68 (₱12.4M)
Funding source:
Outside Infra - GAA 2020 DA FMR
Budget year:
2020
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 39b2ae0cb513… | Sep 24, 2020 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAMARINES SUR 4TH | ₱11,800,948.97 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25FG0059 | Jun 20, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY HARRISON, GARCHITORENA, CAMARINES SUR | On-Going | ₱37.6M |
| 25FG0056 | Jun 3, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, ZONE 2 AND ZONE 4, BARANGAY DANGLA, GARCHITORENA, CAMARINES SUR | On-Going | ₱7.6M |
| 25FG0007 | Apr 4, 2025 | CONSTRUCTION OF MISSING LINKS/NEW ROADS, MANAGNAG (TIGAON-GOA-SN JOSE-LAGONOY-GUIJALO VIA SAN VICENTE ROAD) HIMANAG ROAD, CAMARINES SUR, LAGONOY, CAMARINES SUR | On-Going | ₱65.4M |
| 25FG0025 | Apr 4, 2025 | CONSTRUCTION OF MISSING LINKS/NEW ROADS, LAGONOY-CARAMOAN ROAD (ASON SECTION) GARCHITORENA, CAMARINES SUR | On-Going | ₱65.5M |
| 24FG0128 | Aug 21, 2024 | CONCRETING OF BRGY. LIDONG FMR, BRGY. LIDONG, PRESENTACION, CAMARINES SUR | Completed | ₱9.6M |
| 24FG0121 | Jul 23, 2024 | CONSTRUCTION OF LALUD-GARCHITORENA ROAD (SAGRADA SECTION) STA.37+200 - STA.39+200 (PACKAGE 8), GARCHITORENA, CAMARINES SUR | On-Going | ₱144.8M |
| 24FG0109 | Jul 3, 2024 | CONSTRUCTION OF LALUD - GARCHITORENA ROAD (BAHI-AZON SECTION) STA.48+765 - STA. 50+765 (PACKAGE 11) GARCHITORENA, CAMARINES SUR | On-Going | ₱144.8M |
| 24FG0106 | Jun 19, 2024 | CONSTRUCTION OF LALUD - GARCHITORENA ROAD (SAGRADA SECTION) STA.40+200 - STA. 42+200 (PACKAGE 9), GARCHITORENA, CAMARINES SUR | On-Going | ₱144.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.