Project 20GB0074
DPWH infrastructure contract
Contract ID:
20GB0074
Fingerprint:
1107c076bcc389…da34d584af Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Nov 25, 2020 (5 yrs 11 mo ago) · Target/actual end Dec 21, 2022
Description:
ROAD WIDENING ILOILO-ANTIQUE ROAD K0202+000-K0203+407, K0204+200-K0205+542, SEBASTE, ANTIQUE
Category:
Roads
Implementing office:
DPWH Antique DEO · Region VI
Contractor:
NEWBIG FOUR J CONSTRUCTION INC. · DPWH contractor code 15104
As listed: NEWBIG FOUR J CONSTRUCTION INC. (FORMERLY: FOUR J CONSTRUCTION)
Contract amount:
₱93,654,925.06 (₱93.7M)
Funding source:
Regular Infra - GAA 2020 LP
Budget year:
2020
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| b05f6cc64849… | Nov 19, 2020 | DPWH - ANTIQUE DISTRICT ENGINEERING OFFICE | ₱90,825,053.51 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GB0139 | Jan 12, 2026 | CONSTRUCTION OF CLASSROOMS, TABOC ES, LIBERTAD, ANTIQUE | On-Going | ₱4.6M |
| 25GB0014 | Mar 27, 2025 | ACCESS ROAD LEADING TO KAMALASAG FALLS, BARANGAY ABIERA, SEBASTE, ANTIQUE | On-Going | ₱9.8M |
| 25GB0035 | Mar 27, 2025 | REHABILITATION/MAJOR REPAIR OF BRIDGE -QUIABANAN BR.(B00362PN) ALONG ILOILO-ANTIQUE RD,SEBASTE,ANTIQUE | Completed | ₱19.6M |
| 25GB0036 | Mar 27, 2025 | REHABILITATION/MAJOR REPAIR OF BRIDGE-ABIERA BR. 2 (B00365PN) ALONG ILOILO-ANTIQUE RD,SEBASTE, ANTIQUE | Completed | ₱19.6M |
| 25G00011 | Mar 6, 2025 | REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGES - BACALAN BR. (B00361PN) ALONG ILOILO-ANTIQUE RD | On-Going | ₱47.8M |
| 25GB0037 | Mar 4, 2025 | REHABILITATION/MAJOR REPAIR OF BRIDGE- VIEJO BR. (B00366PN) ALONG ILOILO-ANTIQUE RD, SEBASTE, ANTIQUE | On-Going | ₱19.6M |
| 25GB0038 | Mar 4, 2025 | REHABILITATION/MAJOR REPAIR OF BRIDGE- YPAYO BR. (B00367PN) ALONG ILOILO-ANTIQUE RD SEBASTE, ANTIQUE | On-Going | ₱19.6M |
| 25GB0049 | Mar 4, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY AGUILA, SEBASTE, ANTIQUE | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.