Project 20GG0067
DPWH infrastructure contract
Contract ID:
20GG0067
Fingerprint:
18516e18b177e8…fc1edd11a3 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 25, 2020 (6 yrs ago) · Target/actual end Jan 8, 2021
Description:
RECONSTRUCTION TO CONCRETE PAVEMENT - POTOTAN - TINA - LAMBUNAO ROAD, K0038 + 290 - K0038 + 530
Category:
Roads
Implementing office:
DPWH Iloilo 2nd DEO · Region VI
Contractor:
KIT'Z CONSTRUCTION AND SUPPLY · DPWH contractor code 36392
Contract amount:
₱4,540,000.00 (₱4.5M)
Funding source:
Regular Infra - GAA 2020 OO-1
Budget year:
2020
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| d27d89030c5a… | Oct 6, 2020 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ILOILO 2ND DISTRIC | ₱4,540,000.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GR0058 | Feb 26, 2026 | REPAIR/REHABILITATION OF CLASSROOMS, BACAN ES, CABATUAN, ILOILO | On-Going | ₱4.7M |
| 25GR0059 | Feb 26, 2026 | REPAIR/REHABILITATION OF CLASSROOMS, IGANG ES, POTOTAN, ILOILO | Completed | ₱6.5M |
| 25GR0054 | Sep 15, 2025 | IMPROVEMENT OF INTERSECTION AT ILOILO-CAPIZ (NEW ROUTE) - K0029 + 260 | On-Going | ₱14.7M |
| 25GR0050 | Aug 1, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, POTOTAN, ILOILO | On-Going | ₱3.7M |
| 25GG0179 | Jul 7, 2025 | CONSTRUCTION OF BRIDGE, BARANGAY CATO-OGAN TO BARANGAY CAU-AYAN, POTOTAN, ILOILO | On-Going | ₱48.9M |
| 25GR0016 | Jul 7, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG JALAUR RIVER, BARANGAY BONGCO, POTOTAN, ILOILO | Completed | ₱38.8M |
| 25GR0017 | Jul 7, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG JALAUR RIVER, BARANGAY CANSILAYAN, POTOTAN, ILOILO | On-Going | ₱21.5M |
| 25GR0018 | Jul 7, 2025 | CONSTRUCTION OF FLOOD CONTROL/SLOPE PROTECTION ALONG SUAGE RIVER, GUIBUANGAN, POTOTAN, ILOILO | On-Going | ₱19.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.