DPWH infrastructure contract
Contract ID:
20GI0078
Fingerprint:
dcba52a63f9eba…6a684dcef8 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 1, 2020 (5 yrs 11 mo ago) · Target/actual end Apr 27, 2021
Description:
CONCRETING OF LAYLAYAN-BAGSAKAN-PUNONG-BUGANG BARANGAY ROAD, ALIMODIAN, ILOILO
Category:
Roads
Implementing office:
DPWH Iloilo 4th DEO · Region VI
Contractor:
CAMCU CONSTRUCTION AND SUPPLIES · DPWH contractor code 18507
As listed: CAMCU CONSTRUCTION & SUPPLIES
Contract amount:
₱19,799,792.31 (₱19.8M)
Funding source:
Regular Infra - GAA 2020 LP
Budget year:
2020
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 62bcd285a4f2… | Nov 19, 2020 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ILOILO 4TH DEO | ₱18,798,019.12 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GI0085 | Sep 9, 2025 | CONSTRUCTION OF SCHOOL BUILDING, SINAMAY ELEMENTARY SCHOOL, BARANGAY SINAMAY, ALIMODIAN, ILOILO | On-Going | ₱9.9M |
| 25GI0087 | Sep 9, 2025 | CONSTRUCTION OF SCHOOL BUILDING, ALIMODIAN NATIONAL COMPREHENSIVE HIGH SCHOOL, ALIMODIAN, ILOILO | On-Going | ₱24.6M |
| 25GI0053 | May 20, 2025 | CONSTRUCTION OF ROAD, BARANGAY QUINASPAN, ALIMODIAN, ILOILO | Completed | ₱9.8M |
| 25GI0060 | May 20, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LAYLAYAN, ALIMODIAN, ILOILO | On-Going | ₱4.9M |
| 25GI0061 | May 20, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BANCAL ELEMENTARY SCHOOL, ALIMODIAN, ILOILO | Completed | ₱4.9M |
| 25GI0063 | May 20, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, SITIO KANANGHAN, BARANGAY BUGA, LEON, ILOILO | Completed | ₱4.9M |
| 25GI0040 | Mar 25, 2025 | OFF-CARRIAGEWAY IMPROVEMENT: PAVING OF SHOULDERS - MANDURRIAO-SN MIGUEL- ALIMODIAN-MAASIN-CABATUAN RD - K0023 + 089 - K0023 + 860 | Completed | ₱34.6M |
| 25GI0064 | Mar 11, 2025 | CONSTRUCTION OF AGANAN FLOOD CONTROL STRUCTURE, JARO-AGANAN RIVER, BARANGAY POBLACION, ALIMODIAN, ILOILO | Completed | ₱45.1M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.