["dpwh","20GK0221","CONSTRUCTION OF RAINWATER COLLECTION SYSTEM (RWCS): 1. LABI-LABI NATIONAL HIGH SCHOOL,TOBOSO, NEGROS OCCIDENTAL; 2. LABI-LABI ELEMENTARY SCHOOL,TOBOSO, NEGROS OCCIDENTAL; 3. TEOFILO AMANTE ELEMENTARY SCHOOL, ESCALANTE CITY, NEGROS OCCIDENTAL; 4. CADUHA-AN","Water Provision and Storage","Completed",3996000,0,100,"Negros Occidental 1st DEO","Negros Island Region","SUNSHINE SAPPHIRE CONSTRUCTION AND SUPPLY, INC. (FORMERLY: SUNSHINE SAPPHIRE CONSTRUCTION & SUPPLY) (41567)","2020-07-20","2020-09-07",2020,"Regular Infra - GAA 2020 CSSP",10.85618,123.5069,"1804509000","1804500000"]
SHA-256
b0c1c4e72c68bfd223afaf94aba0f4eb2286e058a3f99a603adf6d8830c7622c