Project 20HJ0010
DPWH infrastructure contract
Contract ID:
20HJ0010
Fingerprint:
36c41ca04e9b3d…bf218b9942 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 8, 2020 (5 yrs 11 mo ago) · Target/actual end May 14, 2021
Description:
ASSET PRESERVATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-TERTIARY ROADS ALONG GUIHULNGAN- BALOC-ISABELA RD. - K0124+595-K0124+987, GUIHULNGAN CITY, NEGROS ORIENTAL
Category:
Roads
Implementing office:
DPWH Negros Oriental 1st DEO · Negros Island Region
Contractor:
BIG JOE'S ENTERPRISES · DPWH contractor code 33601
Contract amount:
₱9,800,000.00 (₱9.8M)
Funding source:
Regular Infra - GAA 2020 OO-1
Budget year:
2020
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 3be52005e739… | Nov 25, 2020 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NEGROS ORIENTAL 1S | ₱9,308,526.22 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26RG0101 | Jul 24, 2026 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-SECONDARY ROADS-GUIHULNGAN-BALOC-ISABELA RD - K0119 + 000 - K0119 + 499, K0121 + 000 - K0121 + 917, K0147 + 862 - K0148 + 000 | On-Going | ₱35.9M |
| 26RG0108 | Jul 8, 2026 | ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGES- KINAYAN BR. (B00134NR) ALONG DUMAGUETE NORTH RD. (JCT BAIS-KABANKALAN-NEGROS OCC BDRY), GUIHULNGAN CITY, NEGROS ORIENTAL | On-Going | ₱54.9M |
| 25RG0189 | Apr 7, 2026 | LAST MILE SCHOOLS PROGRAM - DADIANGAO ES, CITY OF GUIHULNGAN, NEGROS ORIENTAL | On-Going | ₱14.1M |
| 25RG0195 | Apr 7, 2026 | REPAIR/REHABILITATION OF CLASSROOMS, DADIANGAO ES, CITY OF GUIHULNGAN, NEGROS ORIENTAL | Completed | ₱1.6M |
| 25RG0113 | Jul 22, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - EVACUATION CENTER/ QUARANTINE FACILITIES/ PUBLIC HEALTH FACILITIES - COMPLETION OF EVACUATION CENTER/ COVERED COURT, BARANGAY BANWAGUE, GUIHULNGAN CITY, NEGROS ORIENTAL | Completed | ₱3.0M |
| 25RG0041 | Jul 7, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MABUNGA, GUIHULNGAN CITY, NEGROS ORIENTAL | Completed | ₱1.9M |
| 25RG0042 | Jul 7, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MAGSAYSAY, GUIHULNGAN CITY, NEGROS ORIENTAL | Completed | ₱1.9M |
| 25RG0114 | Jul 7, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BASAK, GUIHULNGAN CITY, NEGROS ORIENTAL | Completed | ₱1.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.