Project 20IB0001
DPWH infrastructure contract
Contract ID:
20IB0001
Fingerprint:
c6528b86821fea…5c4baad59e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 3, 2020 (5 yrs 11 mo ago) · Target/actual end Nov 5, 2021
Description:
OFF-CARRIAGEWAY IMPROVEMENT - SECONDARY ROADS JCT. BUENAVISTA - LAWAAN-MARABUT ROAD, K0953+638 - K0954+000, K0954+611 - K0954+836, K0970+150 - K0970+778, K0970+900 - K0972+003, K0972+380 - K0972+917, K0972+877 - K0972+929, K0972+965 - K0973+104, K0973+2
Category:
Roads
Implementing office:
DPWH Eastern Samar DEO · Region VIII
Contractor:
888 ACY ENTERPRISES · DPWH contractor code 32898
Contract amount:
₱71,152,284.25 (₱71.2M)
Funding source:
Regular Infra - GAA 2020 OO-1
Budget year:
2020
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 2f428548c7e1… | Nov 20, 2020 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - EASTERN SAMAR DEO | ₱68,587,161.53 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26IB0094 | Jun 29, 2026 | ASSET PRESERVATION PROGRAM. PREVENTIVE MAINTENANCE - SECONDARY ROADS JCT. BUENAVISTA-LAWAAN-MARABUT RD, K0974+165 - K0988+700 (ROAD REBLOCKING) K0974+165 - K0988+700 | On-Going | ₱25.6M |
| 25IB0046 | Jun 3, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY 2, BALANGIGA, EASTERN SAMAR | Completed | ₱4.9M |
| 24I00292 | May 14, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BARANGAY SAN MIGUEL PROTECTING NATIONAL ROAD AND BRIDGES, BALANGIGA, EASTERN SAMAR LD | On-Going | ₱144.7M |
| 24IB0054 | Jun 13, 2024 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE (DRAINAGE SYSTEM), BARANGAY TABOK, LLORENTE, EASTERN SAMAR | Completed | ₱6.4M |
| 24IB0072 | Jun 13, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, EASTERN SAMAR STATE UNIVERSITY BALANGIGA CAMPUS, BALANGIGA, EASTERN SAMAR | Completed | ₱39.2M |
| 24IB0106 | Jun 13, 2024 | CONSTRUCTION OF ROAD, BARANGAY GUINMAAYUHAN, BALANGIGA, EASTERN SAMAR | On-Going | ₱29.6M |
| 24IB0113 | Jun 13, 2024 | BIP-ACCESS ROADS AND /OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES, CONSTRUCTION OF BRIDGE, BRGY. SUNG-AN, MERCEDES, EASTERN SAMAR | Completed | ₱14.8M |
| 24IB0089 | May 30, 2024 | CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING, GIPORLOS CENTRAL ELEMENTARY SCHOOL, BARANGAY 08, GIPORLOS, EASTERN SAMAR | Completed | ₱5.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.