Project 20J00028
DPWH infrastructure contract
Contract ID:
20J00028
Fingerprint:
5080fc5bb968d6…a04ad044b5 Verified
Status:
On-Going
Physical progress:
100%
Timeline:
Start Nov 24, 2020 (5 yrs 11 mo ago)
Description:
PAVING OF UNPAVED ROADS - SECONDARY ROADS - ZAMBOANGA WEST COASTAL ROAD (SIBUCO - SIRAWAI SECTION)
Category:
Roads
Implementing office:
DPWH Region IX · Region IX
Contractor:
M. ABUBAKAR CONST. AND ENGINEERING, INC. · DPWH contractor code 36365
Contract amount:
₱142,945,372.37 (₱142.9M)
Funding source:
Regular Infra - GAA 2020 OO-1
Budget year:
2020
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25JJ0001 | Mar 27, 2025 | PREVENTIVE MAINTENANCE - SECONDARY ROADS, ZAMBOANGA WEST COASTAL RD (SIBUCO-LIMPAPA SECTION) - (S01152MN) CHAINAGE 5761 - CHAINAGE 9030 | On-Going | ₱55.3M |
| 25JJ0003 | Mar 27, 2025 | REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, ZAMBOANGA WEST COASTAL RD (SIBUCO-LIMPAPA SECTION) - CHAINAGE 13301 - CHAINAGE 13521 | Completed | ₱5.0M |
| 25JJ0005 | Mar 27, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD - K2120 + 179 - K2120 + 311, K2120 + 364 - K2120 + 409 | Completed | ₱53.9M |
| 25JJ0006 | Mar 27, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD - K2112 + 440 - K2112 + 500, K2119 + 149 - K2119 + 192, K2120 + 075 - K2120 + 105 | Completed | ₱15.4M |
| 25JJ0007 | Mar 27, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD - K2122 + 600 - K2122 + 635, K2123 + 140 - K2123 + 156 | Completed | ₱10.3M |
| 25JJ0011 | Mar 27, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD - K2135 + 871 - K2135 + 907, K2136 + 316 - K2136 + 358 | On-Going | ₱34.7M |
| 25JJ0012 | Mar 27, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD - K2140 + 301 - K2140 + 334, K2143 + 326 -K2143 + 352, K2143 + 478 - K2143 + 518 | Completed | ₱23.8M |
| 25JJ0013 | Mar 27, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD - K2144 + 033 - K2144 + 091, K2144 + 728 - K2144 + 752, K2144 + 902 - K2144 + 942 | Completed | ₱34.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.