FY2026 GAA: ₱6.79T
PisoScan

Project 20KC0012

DPWH infrastructure contract
Contract ID:
20KC0012
Fingerprint:
d0d7764d7d9ae8…d8f2e5a4a1 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 20, 2020 (6 yrs 8 mo ago) · Target/actual end Jul 13, 2020
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. POBLACION, KALILANGAN, BUKIDNON
Category:
Buildings and Facilities
Implementing office:
Contractor:
KEZ ENTERPRISES · DPWH contractor code 25556
Contract amount:
₱1,980,000.00 (₱2.0M)
Funding source:
Regular Infra - GAA 2020 LP
Budget year:
2020

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
beb438197da3…Feb 5, 2020DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BUKIDNON 3RD DEO₱1,900,739.05

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25KN0064Feb 16, 2026CONSTRUCTION OF CLASSROOMS, PASAYANON ES, KALILANGAN, BUKIDNONOn-Going₱2.9M
25KN0065Feb 16, 2026CONSTRUCTION OF SCHOOL HEALTH FACILITIES, KALILANGAN CES, KALILANGAN, BUKIDNONCompleted₱2.9M
25K00426Jul 11, 2025CONSTRUCTION OF ONE (1) UNIT 4-STOREY 12 DOORS QUARTERING FACILITY FOR OFFICER'S QUARTERSOn-Going₱111.3M
25K00427Jul 11, 2025CONSTRUCTION OF ONE (1) UNIT 4-STOREY 12 DOORS QUARTERING FACILITY FOR ENLISTED PERSONNELOn-Going₱85.7M
25K00243May 30, 2025PREVENTIVE MAINTENANCE-SECONDARY RODS, BUKIDNON BDRY-NORTH COTABATO RD (S01606MN) - CHAINAGE 0 - CHAINAGE 10000On-Going₱235.4M
25KN0052May 23, 2025CONCRETING OF SITIO DARUSALAM, BRGY. NINOY AQUINO FMR, BRGY. NINOY AQUINO, KALILANGAN, BUKIDNONOn-Going₱14.6M
25KN0009Mar 26, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BARORAWON, KALILANGAN, BUKIDNONOn-Going₱12.9M
25KN0042Mar 25, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BANGBANG, KALILANGAN, BUKIDNONOn-Going₱12.6M