Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 20KC0081

DPWH infrastructure contract
Contract ID:
20KC0081
Fingerprint:
05f15b846b3ce5…e0b8402eed Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 26, 2020 (6 yrs 2 mo ago) · Target/actual end Apr 2, 2021
Description:
CONSTRUCTION OF 1STY 2CL SCHOOL BUILDING, MIGPAIT ES, INDULANG, TALAKAG, BUKIDNON
Category:
Buildings and Facilities
Implementing office:
Contractor:
AMMAR CONSTRUCTION AND ENTERPRISES · DPWH contractor code 35325
Contract amount:
₱5,368,354.58 (₱5.4M)
Funding source:
Outside Infra - GAA 2020 DepEd BEFF
Budget year:
2020

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
40a04eb8cd34…Aug 17, 2020DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BUKIDNON 3RD DEO₱4,880,322.35

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25K00428Aug 12, 2025CONSTRUCTION OF RAINWATER COLLECTORS SYSTEM (RWCS) IN PUBLIC FACILITIESOn-Going₱7.5M
25KC0101Jul 28, 2025PREVENTIVE MAINTENANCE ALONG JCT. SH AGLAYAN-ALANIB-TICALAAN ROAD (TICALAAN-PAGANAN SECT.) K1503+200-K1504+754, K1506+910-K1507+000, K1507+000-K1508+000, TALAKAG, BUKIDNONCompleted₱95.1M
25KC0129Jul 28, 2025PREVENTIVE MAINTENANCE ALONG JCT. SH-AGLAYAN-ALANIB-TICALAAN ROAD (TICALAAN-PAGANAN SECT.) K1504+754 - K1506+910, K1508+000 - K1508+364, TALAKAG, BUKIDNONCompleted₱94.5M
25K00196Jul 2, 2025CONST. OF BY-PASS AND DIVERSION ROADS,TALAKAG BYPASS ROAD, BUKIDNONOn-Going₱62.7M
25KC0131Jun 30, 2025PREVENTIVE MAINTENANCE ALONG JCT. SH-AGLAYAN-ALANIB-TICALAAN ROAD (TICALAAN-PAGANAN SECT.) - K1509+079-K1514+169, TALAKAG, BUKIDNONCompleted₱94.5M
25KC0106Jun 13, 2025CONSTRUCTION OF JCT. CDO-DOMINOROG-CAMP KIBARITAN RD. TINONTONGAN, LANTUD, TALAKAG, BUKIDNONOn-Going₱48.9M
25K00197May 26, 2025CONSTRUCTION OF JCT. CAMP KIBARITAN-PANGANTUCAN - JCT GUINOYURAN-VALENCIA ROAD, PACKAGE 11, BUKIDNONOn-Going₱141.8M
25KC0108May 23, 2025CONSTRUCTION OF ROAD LEADING TO MINDAMORA FALLS WITH VIEW DECK BARANGAY LANTUD, TALAKAG, BUKIDNONOn-Going₱96.4M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.