Project 20KI0009

DPWH infrastructure contract
Contract ID:
20KI0009
Fingerprint:
819cd57ed11ad6…1a77f6e53d Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 19, 2020 (6 yrs 7 mo ago) · Target/actual end Oct 12, 2020
Description:
NETWORK DEVELOPMENT-ROAD WIDENING - SECONDARY ROADS CALAMBA-BALIANGAO ROAD, K1782+379-K1785+086, BALIANGAO, MISAMIS OCCIDENTAL.
Category:
Roads
Implementing office:
Contractor:
Contract amount:
₱91,204,545.12 (₱91.2M)
Funding source:
Regular Infra - GAA 2020 OO-1
Budget year:
2020

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26KI0031Jul 16, 2026NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS - CALAMBA-BALIANGAO RD - K1790+000 - K1790+950On-Going₱33.3M
25KI0008Mar 2, 2025ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - OROQUIETA CITY - PLARIDEL - CALAMBA - SAPANG DALAGA RD - K1785+080 - K1785+170Completed₱47.5M
24KI0079Jun 10, 2024ASSET PRESERVATION PROGRAM - REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - PRIMARY ROADS - OROQUIETA CITY - PLARIDEL - CALAMBA - SAPANG DALAGA RD - K1784+400 - K1785+000Completed₱49.0M
24KI0005Mar 7, 2024REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY NORTHERN POBLACION, BALIANGAO MISAMIS OCCIDENTAL.Completed₱6.7M
23KI0101Sep 10, 2023CONSTRUCTION OF SOLAR WATER SYSTEM, BRGY. PUNTA MIRAY, MUNICIPALITY OF BALIANGAO, MISAMIS OCCIDENTAL.Completed₱9.5M
23KI0095Aug 13, 2023REHABILITATION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY DEL PILAR, BALIANGAO, MISAMIS OCCIDENTAL.Completed₱1.9M
23KI0097Aug 13, 2023REHABILITATION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY LIBERTAD, CALAMBA, MISAMIS OCCIDENTAL.Completed₱2.9M
23KI0043May 15, 2023REHABILITATION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY PUNTA SULONG, BALIANGAO, MISAMIS OCCIDENTAL.Completed₱1.9M