FY2026 GAA: ₱6.79T
PisoScan

Project 20MD0112

DPWH infrastructure contract
Contract ID:
20MD0112
Fingerprint:
5abcd016039ef3…444a23c217 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Nov 18, 2020 (5 yrs 11 mo ago) · Target/actual end Feb 3, 2021
Description:
CONCRETING OF SINAPANGAN-KILOYAO ROADS, LIBUNGAN, NORTH COTABATO
Category:
Roads
Implementing office:
DPWH Cotabato 1st DEO · Region XII
Contractor:
SUNSTONE CONSTRUCTION & SUPPLY · DPWH contractor code 11122
Contract amount:
₱9,574,573.34 (₱9.6M)
Funding source:
Regular Infra - GAA 2020 LP
Budget year:
2020

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
98c572214868…Nov 10, 2020DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NORTH COTABATO 2ND₱9,574,573.34

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25MD0073Sep 8, 2025CONSTRUCTION OF SCHOOL BUILDING, MALENGEN ELEMENTARY SCHOOL, BARANGAY MALENGEN, LIBUNGAN, COTABATOCompleted₱4.9M
25MD0060Jun 5, 2025CONSTRUCTION OF LATERAL A2 SERVICE ROAD ALONG CABPANGI ROAD, LIBUNGAN, COTABATOCompleted₱6.7M
25MD0058Apr 15, 2025LAWILI-PALACAT-BAO ROAD IN SUPPORT OF BANANA, CORN, COCONUT, AND PALM OIL INDUSTRIES, ALAMADA-ALEOSAN, NORTH COTABATOCompleted₱46.8M
25MD0022Mar 7, 2025INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (GUARDRAILS, ROAD SIGNS, PAVEMENT MARKINGS, ROADWAY LIGHTING) ALONG BANISILAN-GUILING-ALAMADA-LIBUNGAN RD, LIBUNGAN, NORTH COTABATOCompleted₱46.8M
25MD0004Mar 6, 2025CONSTRUCTION OF PUROK 3 - PUROK 4 - PUROK 5, ROAD, BARANGAY CABPANGI, LIBUNGAN, NORTH COTABATOCompleted₱4.9M
25MD0023Mar 6, 2025CONSTRUCTION OF ROAD, DEMAPACO - SITIO MISULO, BARANGAY DEMAPACO, LIBUNGAN, NORTH COTABATOCompleted₱4.9M
24M00275Jan 15, 2025COMPLETION OF GENERAL ACADEMIC BUILDING, LIBUNGAN CAMPUS-UNIVERSITY OF SOUTHERN MINDANAO, LIBUNGAN, NORTH COTABATOOn-Going₱19.8M
24MD0050Aug 30, 2024CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LIBUNGAN RIVER (UPSTREAM AND DOWNSTREAM OF GREBONA BRIDGE-GREBONA SECTION), BARANGAY GREBONA, LIBUNGAN, NORTH COTABATOCompleted₱96.3M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.