FY2026 GAA: ₱6.79T
PisoScan

Project 20MG0026

DPWH infrastructure contract
Contract ID:
20MG0026
Fingerprint:
7c453835ff41ab…5933e320d2 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 17, 2020 (6 yrs 8 mo ago) · Target/actual end May 16, 2020
Description:
CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. LAPUZ, NORALA, SOUTH COTABATO
Category:
Buildings and Facilities
Implementing office:
Contractor:
GOLDEN A NINE CONSTRUCTION · DPWH contractor code 46558
Contract amount:
₱1,184,999.84 (₱1.2M)
Funding source:
Regular Infra - GAA 2020 LP
Budget year:
2020

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
94274e7381ea…Jan 27, 2020DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SOUTH COTABATO 1ST₱1,184,999.84

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25MG0121Feb 6, 2026REPAIR/REHABILITATION OF CLASSROOMS, NORALA CENTRAL ELEMENTARY SCHOOL, NORALA, SOUTH COTABATOOn-Going₱23.3M
25MG0108Jun 27, 2025CONCRETING OF PUROK BALITE TO CROSSING BUNGOT, BRGY. SAN JOSE FMR (PHASE II), BRGY. SAN JOSE, NORALA, SOUTH COTABATOCompleted₱14.7M
25MG0088Jun 20, 2025CONSTRUCTION OF MULTI PURPOSE BUILDING AT BARANGAY KIBID, NORALA, SOUTH COTABATOCompleted₱4.9M
24M00194Mar 7, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY POBLACION, NORALA, SOUTH COTABATOOn-Going₱7.0M
25MG0048Feb 28, 2025CONSTRUCTION OF RIVERBANK PROTECTION ALONG BANGA RIVER, BARANGAY KIBID, NORALA, SOUTH COTABATOCompleted₱34.3M
24M00281Feb 25, 2025CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - NORALA SUPER HEALTH CENTER, SOUTH COTABATOOn-Going₱9.6M
24MG0139Sep 13, 2024CLUSTER XIII-A.CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN DATAL BILA INTEGRATED SCHOOL, BARANGAY TUDOK, T'BOLI, SOUTH COTABATO B.CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN DENLAG INTEGRATED SCHOOL, BARANGAY DENLAG, LAKE SEBU, SOUCompleted₱19.9M
24MG0124Aug 16, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. EL NONOK, BANGA, SOUTH COTABATOCompleted₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.