Project 20MG0088
DPWH infrastructure contract
Contract ID:
20MG0088
Fingerprint:
000babcc120bed…315a3ded07 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 16, 2020 (6 yrs ago) · Target/actual end Jan 18, 2021
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING (BARANGAY HALL), POBLACION, LAKE SEBU, SOUTH COTABATO
Category:
Buildings and Facilities
Implementing office:
DPWH South Cotabato 2nd DEO · Region XII
Contractor:
BARRIST BUILDERS AND CONSTRUCTION SUPPLY · DPWH contractor code 39785
Contract amount:
₱1,760,452.15 (₱1.8M)
Funding source:
Regular Infra - GAA 2020 LP
Budget year:
2020
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 464a359edcb2… | Oct 1, 2020 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SOUTH COTABATO 1ST | ₱1,710,800.64 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26MG0017 | Jun 17, 2026 | CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE-SURALLAH-LAKE SEBU-MAITUM RD-K1745+300-K1745+453 | On-Going | ₱35.2M |
| 26MG0010 | Jun 11, 2026 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-SURALLAH-LAKE SEBU-MAITUM RD-K1757+291-K1757+760 | On-Going | ₱9.1M |
| 26MG0012 | Jun 11, 2026 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-SURALLAH-LAKE SEBU-MAITUM RD-K1759+000-K1761+020 | Completed | ₱21.9M |
| 26MG0011 | Jun 4, 2026 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-SURALLAH-LAKE SEBU-MAITUM RD-K1755+815-K1757+291 | Completed | ₱19.7M |
| 25MG0112 | Aug 20, 2025 | CONSTRUCTION OF SCHOOL BUILDING, UBO ELEMENTARY SCHOOL-LAMFENEK EXTENSION, BARANGAY LAMFUGON, LAKE SEBU, SOUTH COTABATO | Completed | ₱5.0M |
| 25M00052 | Aug 5, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SURALLAH-LAKE SEBU-MAITUM RD - K1799+460 - K1799+580, K1827+970 - K1828+022, LAKE SEBU, SOUTH COTABATO | On-Going | ₱93.6M |
| 25MG0110 | Jun 27, 2025 | CLUSTER I-A.CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM (RWCS), KIANTAY ELEMENTARY SCHOOL, SITIO KIANTAY, BRGY. UPPER SEPAKA, SURALLAH, SOUTH COTABATO B.CONSTRUCTION OF RAINWATER COLLECTOR SYSTEM (RWCS), NEW TUPI IS, SITIO NEW TUPI, BRGY. NED, LAKE SEBU, S | Completed | ₱2.6M |
| 25MG0016 | Apr 11, 2025 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-SURALLAH-LAKE SEBU-MAITUM RD-K1755+262-K1755+815, SOUTH COTABATO | Completed | ₱13.6M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.