Project 20OF0008

DPWH infrastructure contract
Hashed input (canonical JSON of the source row)
["dpwh","20OF0008","CONSTRUCTION OF FLOOD CONTROL STRUCTURES AND TRIBUTARIES, BRGY. HOLY SPIRIT (PHASE 5), QUEZON CITY","GAA 2020 OO-2","Completed",47037576,0,100,"Quezon City 1st DEO","National Capital Region","FRAMECON BUILDERS (22482) / TRICHES CONSTRUCTION & TRADING (33876)","2020-02-19","2021-03-14",2020,"Regular Infra - GAA 2020 OO-2",14.65007,121.02855,"1381300000","1307400000"]
SHA-256
41cc41c04fbb92c70a08d10cdec518b86e1f3163d356f37a85c47b57d430161b

Hash the line above with SHA-256 to reproduce the fingerprint. It proves the record is unchanged since import. It is not a blockchain entry, and it cannot prove the source data is accurate.