Project 20PE0046
DPWH infrastructure contract
Contract ID:
20PE0046
Fingerprint:
515658e902d589…94f9d4babf Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 9, 2020 (6 yrs 8 mo ago) · Target/actual end Aug 3, 2020
Description:
CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJORRIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF FLOOD MITIGATIONSTRUCTURE ALONG AGNO RIVER BASIN, MANGKEW-NABNENG SECTION, KABAYAN, BENGUET
Category:
Flood Control and Drainage
Implementing office:
DPWH Benguet 1st DEO · Cordillera Administrative Region
Contractor:
BTCJR CONSTRUCTION AND ENGINEERING SERVICES · DPWH contractor code 38675
Contract amount:
₱7,327,620.25 (₱7.3M)
Funding source:
Regular Infra - GAA 2020 OO-2
Budget year:
2020
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| c62df399b550… | Feb 12, 2020 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BFED | ₱7,327,620.25 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26PF0019 | Sep 1, 2026 | CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - CONG. ANDRES ACOP COSALAN RD - K0343 + 600, K0344 + 000, K0344 + 800, K0346 + 070, K0346 + 750, K0355 + 650 | On-Going | ₱9.2M |
| 26PE0005 | Jul 16, 2026 | CONSTRUCTION OF CONCRETE ROAD - KALING BRIDGE-LOWER BASHOY-UPPER BABADAK ROAD LEADING TO MT. PULAG - 2+461 - 2+564, KABAYAN, BENGUET | On-Going | ₱4.3M |
| 25PE0083 | Mar 31, 2026 | REPAIR/REHABILITATION OF CLASSROOMS, ADAOAY ES, KABAYAN, BENGUET | On-Going | ₱10.2M |
| 25PE0016 | Mar 31, 2025 | CONSTRUCTION OF CONCRETE ROAD - TIMBAK CAVES ROAD LEADING TO TIMBAK CAVES AND MUMMY OF APO ANNO, ATOK/KABAYAN, BENGUET | Completed | ₱5.3M |
| 25PE0028 | Mar 31, 2025 | CONSTRUCTION OF CONCRETE ROAD - KALING BRIDGE - LOWER BASHOY - UPPER BADABAK ROAD LEADING TO MT. PULAG, KABAYAN, BENGUET | On-Going | ₱9.7M |
| 25PE0012 | Mar 17, 2025 | CONSTRUCTION OF CONCRETE ROAD - POBLACION-KARAO-EKIP ACCESS ROAD LEADING TO MOUNT PURGATORY, BOKOD, BENGUET | Completed | ₱9.8M |
| 25PE0027 | Mar 4, 2025 | RECONSTRUCTION TO CONCRETE PAVEMENT - CONG. ANDRES ACOP COSALAN RD (S00379LZ) - K0326+280 - K0326+432, KABAYAN, BENGUET | Completed | ₱3.6M |
| 25PE0022 | Feb 17, 2025 | CONSTRUCTION OF CONCRETE ROAD - BAGUIO-BONTOC ROAD JCT. TO BATAN-ADAOAY, KABAYAN ROAD IN SUPPORT OF VEGETABLES, PROCESSED TEA AND COFFEE INDUSTRY, KABAYAN, BENGUET | Completed | ₱9.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.