Project 21CC0288
DPWH infrastructure contract
Contract ID:
21CC0288
Fingerprint:
3d68dde0a5f646…90ab4c373d Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 16, 2021 (5 yrs 4 mo ago) · Target/actual end Feb 11, 2022
Description:
CONCRETING OF BRGY. SAN ISIDRO II FMR, BRGY. SAN ISIDRO II, PAOMBONG, BULACAN
Category:
Roads
Implementing office:
DPWH Bulacan 1st DEO · Region III
Contractor:
JCL BUILDERS · DPWH contractor code 44209
Contract amount:
₱12,437,216.92 (₱12.4M)
Funding source:
Outside Infra - GAA 2021 DA FMR
Budget year:
2021
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 7914c3b4e505… | Jul 9, 2021 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BULACAN 1ST DEO | ₱12,063,756.95 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CG0159 | Jun 5, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, APALIT, PAMPANGA | Completed | ₱4.7M |
| 25CC0240 | May 23, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BRGY. FRANCES, CALUMPIT, BULACAN | On-Going | ₱14.5M |
| 25CC0282 | May 23, 2025 | CONSTRUCTION OF ROAD AT BARANGAY GATBUCA, CALUMPIT, BULACAN | On-Going | ₱8.6M |
| 25CC0348 | May 23, 2025 | CONSTRUCTION OF ROAD WITH DRAINAGE AT BARANGAY CALIZON-BULUSAN-STA. LUCIA CALUMPIT, BULACAN | On-Going | ₱48.0M |
| 25CC0357 | May 23, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY STA. LUCIA, CALUMPIT, BULACAN | On-Going | ₱4.9M |
| 25CC0359 | May 23, 2025 | CONSTRUCTIION OF ROAD AT BARANGAY PUNGO, CALUMPIT, BULACAN | On-Going | ₱19.3M |
| 25CC0539 | May 23, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LONGOS, CALUMPIT, BULACAN | On-Going | ₱14.5M |
| 25CC0264 | Apr 8, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY PANDUCOT, CALUMPIT, BULACAN | On-Going | ₱14.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.