Project 21CE0087
DPWH infrastructure contract
Contract ID:
21CE0087
Fingerprint:
551c003888d84f…e30c6ff001 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 16, 2021 (5 yrs 8 mo ago) · Target/actual end May 16, 2021
Description:
CONSTRUCTION OF ROAD FROM BARANGAY BAGONG BAYAN TO BARANGAY SAN FELIPE, LLANERA, NUEVA ECIJA
Category:
Roads
Implementing office:
DPWH Nueva Ecija 1st DEO · Region III
Contractor:
EUCLIDCON BUILDERS · DPWH contractor code 45287
Contract amount:
₱4,855,951.31 (₱4.9M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| cb65d3745674… | Feb 4, 2021 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NUEVA ECIJA 1ST DE | ₱4,855,951.31 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CE0195 | Jun 30, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY GEN. RICARTE, LLANERA, NUEVA ECIJA | Completed | ₱5.9M |
| 25CE0196 | Jun 30, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY VICTORIA, LLANERA, NUEVA ECIJA | Completed | ₱4.9M |
| 25CE0256 | Mar 25, 2025 | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS, JCT PINAGPANAAN-RIZAL-PANTABANGAN RD - K0136 + 000 - K0137 + 000 | Completed | ₱14.7M |
| 25CE0109 | Mar 20, 2025 | REHABILITATION OF ROAD, BARANGAY SANTA BARBARA TO BARANGAY VILLA VINIEGAS, LLANERA, NUEVA ECIJA | Completed | ₱9.7M |
| 25CE0140 | Feb 17, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BAGUMBAYAN, LLANERA, NUEVA ECIJA | Completed | ₱3.9M |
| 25CE0102 | Feb 14, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY VICTORIA, LLANERA, NUEVA ECIJA | Completed | ₱4.7M |
| 25CE0112 | Feb 14, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY PLARIDEL, LLANERA, NUEVA ECIJA | Completed | ₱4.0M |
| 25CE0113 | Feb 11, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SAN FRANCISCO, LLANERA, NUEVA ECIJA | Completed | ₱2.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.