Project 21CJ0004
DPWH infrastructure contract
Contract ID:
21CJ0004
Fingerprint:
1680b3b1636859…23583c8f4f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 8, 2021 (5 yrs 8 mo ago) · Target/actual end Aug 8, 2021
Description:
FLOOD MANAGEMENT PROGRAM CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS CONSTRUCTION OF FLOOD CONTROL STRUCTURES WITHIN AGNO RIVER BASIN SYSTEM, ALONG CAMILING RIVER RIGHT BANK (PACKAGE C), BILAD
Category:
Flood Control and Drainage
Implementing office:
DPWH Tarlac DEO · Region III
Contractor:
STO. CRISTO CONSTRUCTION & TRADING INC. (FOR: STO. CRISTO CONSTRUCTION & TRADING) · DPWH contractor code 26096
Contract amount:
₱23,349,452.72 (₱23.3M)
Funding source:
Regular Infra - GAA 2021 OO-2
Budget year:
2021
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 4bfc97539e3c… | Feb 18, 2021 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - TARLAC 1ST DEO | ₱23,349,452.72 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26CJ0075 | Jun 30, 2026 | REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS PANIQUI-CAMILING-WAWA RD - K0170 + 162 - K0171 + 190 | On-Going | ₱25.4M |
| 25CJ0233 | Jun 20, 2025 | CONSTRUCTION OF CAMILING - BAYAMBANG DIVERSION ROAD (SEGMENT 2), CAMILING, TARLAC | Completed | ₱96.5M |
| 25CJ0234 | Jun 20, 2025 | CONSTRUCTION OF CAMILING - BAYAMBANG DIVERSION ROAD (SEGMENT 3), CAMILING, TARLAC | On-Going | ₱95.3M |
| 25CJ0240 | Jun 20, 2025 | CONSTRUCTION OF STA. IGNACIA - CAMILING DIVERSION ROAD (SEGMENT 5), TARLAC | Completed | ₱96.5M |
| 25CJ0285 | May 22, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (CAMILING PUBLIC MARKET), CAMILING, TARLAC (PACKAGE C) | On-Going | ₱97.8M |
| 25CJ0175 | Apr 8, 2025 | PREVENTIVE MAINTENANCE ROMULO H-WAY - K0152+ 562 - K0154 + 007 | Completed | ₱96.5M |
| 25CJ0177 | Apr 8, 2025 | PREVENTIVE MAINTENANCE PANIQUI-CAMILING-WAWA RD - K0167 + 135 - K0168 + 440 | Completed | ₱96.5M |
| 25CJ0230 | Apr 8, 2025 | REHABILITATION OF CAMILING ROAD NETWORK (ANNEX 3), CAMILING, TARLAC | Completed | ₱96.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.