Project 21DQ0056
DPWH infrastructure contract
Contract ID:
21DQ0056
Fingerprint:
52cea26115e996…c6fd7f11da Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 11, 2021 (5 yrs 1 mo ago) · Target/actual end Jun 7, 2022
Description:
ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF REVETMENT ALONG BACOOR RIVER, BARANGAY SALINAS, PHASE
Category:
Flood Control and Drainage
Implementing office:
DPWH Cavite 3rd DEO · Region IV-A
Contractor:
KLDS TRADING & CONSTRUCTION (28091) / OMNICON BUILDERS · DPWH contractor code 22816
Contract amount:
₱96,375,336.57 (₱96.4M)
Funding source:
Regular Infra - GAA 2021 OO-2
Budget year:
2021
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DQ0110 | Jul 3, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MALIKSI 2, BACOOR CITY, CAVITE | On-Going | ₱9.8M |
| 25DQ0111 | Jul 3, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BAYANAN, BACOOR CITY, CAVITE | On-Going | ₱9.8M |
| 25DF0158 | Jul 1, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITESCONSTRUCTION OF ROAD WITH DRAINAGE AT BRGY. PALICO IV, CITY OF IMUS, | On-Going | ₱4.8M |
| 25DQ0084 | Jun 17, 2025 | CONSTRUCTION OF RIVERWALL AND OTHER IMPROVEMENT WORKS ALONG BACOOR RIVER, PHASE 1, CITY OF BACOOR, CAVITE | On-Going | ₱96.0M |
| 25DQ0085 | Jun 17, 2025 | CONSTRUCTION OF RIVERWALL AND OTHER IMPROVEMENT WORKS ALONG BACOOR RIVER, PHASE 2, CITY OF BACOOR, CAVITE | On-Going | ₱98.0M |
| 25DQ0090 | Jun 17, 2025 | CONSTRUCTION OF SLOPE AND BANKS PROTECTION WORKS ALONG BACOOR RIVER, CITY OF BACOOR, CAVITE (PHASE 1) | On-Going | ₱98.0M |
| 25DQ0099 | Jun 17, 2025 | CONSTRUCTION OF SLOPE AND BANKS PROTECTION WORKS ALONG BACOOR RIVER, CITY OF BACOOR, CAVITE (PHASE 3) | On-Going | ₱98.0M |
| 25DQ0101 | Jun 17, 2025 | CONSTRUCTION OF SLOPE AND BANKS PROTECTION WORKS ALONG BACOOR RIVER, CITY OF BACOOR, CAVITE (PHASE 2) | On-Going | ₱98.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.