Project 21EH0072
DPWH infrastructure contract
Contract ID:
21EH0072
Fingerprint:
c865159e089468…c13c26faad Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jan 31, 2022 (4 yrs 9 mo ago) · Target/actual end May 13, 2022
Description:
CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING/MULTI-PURPOSE HALL AT BRGY. AGPUDLOS, SAN ANDRES, ROMBLON
Category:
GAA 2021 LP
Implementing office:
DPWH Romblon DEO · MIMAROPA Region
Contractor:
R.G. FLORENTINO CONST. & TRADING INC. · DPWH contractor code 18301
Contract amount:
₱1,963,916.23 (₱2.0M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25EH0167 | Jul 29, 2025 | CONSTRUCTION OF 7 RAINWATER COLLECTION SYSTEM (RWCS), TABLAS ISLAND, ROMBLON | Completed | ₱2.6M |
| 25EH0151 | May 27, 2025 | CONSTRUCTION OF ROAD, AGPUDLOS LEADING TO RSU ROAD (PHASE 3), SAN ANDRES, ROMBLON | On-Going | ₱46.7M |
| 25EH0121 | May 21, 2025 | CONSTRUCTION OF VICTORIA RIVER FLOOD CONTROL STRUCTURE, SAN ANDRES, ROMBLON | On-Going | ₱119.4M |
| 25EH0030 | Apr 11, 2025 | CONSTRUCTION OF MABINI FLOOD CONTROL STRUCTURE, BARANGAY MABINI, SAN ANDRES, ROMBLON | On-Going | ₱48.3M |
| 25EH0090 | Apr 10, 2025 | CONSTRUCTION OF MARI-SUR FLOOD CONTROL STRUCTURE (RIGHT SIDE), SAN ANDRES, ROMBLON | On-Going | ₱48.3M |
| 25EH0012 | Mar 24, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY VICTORIA, SAN ANDRES, ROMBLON | Completed | ₱4.9M |
| 25EH0062 | Mar 3, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY MABINI, SAN ANDRES, ROMBLON | Completed | ₱2.9M |
| 24EH0131 | Jun 19, 2024 | REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE ALONG PARPAGOHA (MARIGONDON)-BINOOG RD, K0020+900.00 - K0020+985.60, TABLAS ISLAND, ROMBLON | On-Going | ₱82.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.