Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 21FC0131

DPWH infrastructure contract
Hashed input (canonical JSON of the source row)
["dpwh","21FC0131","CONSTRUCTION OF MABULAO RIVER CONTROL STRUCTURE BARANGAY SAN ISIDRO - COBANGBANG SECTION, DAET, CAMARINES NORTE","GAA 2021 OO-2","Completed",42081279.12,0,100,"Camarines Norte DEO","Region V","ARIK CONSTRUCTION (32786) / ED1SON DEVELOPMENT & CONSTRUCTION INC. (2400)","2021-04-30","2021-10-15",2021,"Regular Infra - GAA 2021 OO-2",14.10566,122.96844,"501603000","501600000"]
SHA-256
c2cd0ca2e35629bafe8215bd97c4cdd3b5b423629e1412c936c259a8ac4fb470

Hash the line above with SHA-256 to reproduce the fingerprint. It proves the record is unchanged since import. It is not a blockchain entry, and it cannot prove the source data is accurate.