Physical progress:
100%
Timeline:
Start Aug 19, 2021 (5 yrs 2 mo ago) · Target/actual end Feb 28, 2022
Description:
CONSTRUCTION OF FLOOD CONTROL SYSTEM OF MAHABA CREEK LEADING TO TAMBANG RIVERSTA.0+000.00 - STA.0+290.00 (BOTH SIDES)SITIO PALAYAN, BARANGAY LAMON, GOA, CAMARINES SUR
Category:
Flood Control and Drainage
Implementing office:
DPWH Camarines Sur 4th DEO · Region V
Contractor:
MACROPRIME BUILDERS CORPORATION · DPWH contractor code 23396
As listed: MACROPRIME BUILDERS CORPORATION (FORMERLY: MORANTE BUILDERS & SUPPLY)
Contract amount:
₱19,600,000.00 (₱19.6M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 87c8867a6a7b… | Aug 6, 2021 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAMARINES SUR 4TH | ₱18,600,808.57 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25FG0103 | Jul 30, 2025 | REHABILITATION OF MULTI-PURPOSE BUILDING, GOA, CAMARINES SUR | On-Going | ₱4.7M |
| 25FG0055 | Jun 30, 2025 | CONSTRUCTION OF WATER SUPPLY SYSTEM LEVEL 3 (PHASE-2) GOA AND SAN JOSE, CAMARINES SUR GOA AND SAN JOSE, CAMARINES SUR | On-Going | ₱33.2M |
| 25FG0052 | Jun 20, 2025 | CONSTRUCTION OF ROAD, ZONE 5, SITIO AMOGUIS TO BRGY. TAYTAY, GOA, CAMARINES SUR | Completed | ₱4.7M |
| 25FG0089 | Jun 9, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, GOA, CAMARINES SUR | On-Going | ₱4.8M |
| 25FG0071 | Jun 3, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, PINAGLABANAN NATIONAL HIGH SCHOOL, BARANGAY PINAGLABANAN, GOA, CAMARINES SUR | On-Going | ₱9.5M |
| 25FG0033 | Mar 28, 2025 | CONSTRUCTION OF DRAINAGE CANAL AT CRIS, GOA, CAMARINES SUR | On-Going | ₱4.8M |
| 25FG0020 | Mar 27, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY CATAGBACAN, GOA, CAMARINES SUR | Completed | ₱6.7M |
| 25FG0014 | Mar 21, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY DIGDIGON, GOA, CAMARINES SUR | On-Going | ₱5.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.