Physical progress:
100%
Timeline:
Start May 3, 2021 (5 yrs 6 mo ago) · Target/actual end Dec 28, 2021
Description:
CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS - CONSTRUCTION OF LEVEL III WATER SUPPLY PROJECTS, BACLAYON, BOHOL
Category:
Water Provision and Storage
Implementing office:
DPWH Bohol 1st DEO · Region VII
Contractor:
JA ACHACOSO ENTERPRISES & GENERAL SERVICES · DPWH contractor code 33229
Contract amount:
₱23,990,671.04 (₱24.0M)
Funding source:
Regular Infra - GAA 2021 CSSP
Budget year:
2021
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25HA0070 | Aug 14, 2025 | COMPLETION OF MULTI-PURPOSE BUILDINGS (MONTAÑA, SAN ISIDRO), BACLAYON, BOHOL | Completed | ₱7.8M |
| 25HA0086 | Jun 2, 2025 | CONSTRUCTION OF SCHOOL BUILDING AND CLASSROOMS FOR BACLAYON NATIONAL HIGH SCHOOL, LANDICAN, BACLAYON, BOHOL | On-Going | ₱34.0M |
| 25HA0099 | Jun 2, 2025 | CONSTRUCTION OF ROAD LOCATED AT BAWAL STREET, BARANGAY LANDICAN, BACLAYON, BOHOL | Completed | ₱4.9M |
| 25HA0112 | May 28, 2025 | CONCRETING OF BRGY. SAN ISIDRO TO BRGY. LIBERTAD FMR, SAN ISIDRO, BACLAYON, BOHOL | Completed | ₱11.0M |
| 25HA0046 | Mar 27, 2025 | CONSTRUCTION OF ROAD, BARANGAY BOOL, TAGBILARAN CITY, BOHOL | Completed | ₱19.6M |
| 25HA0082 | Mar 27, 2025 | CONSTRUCTION OF LIBERTAD TO STA. CRUZ (BACLAYON) ROAD, BACLAYON, BOHOL | Completed | ₱9.8M |
| 24H00161 | Dec 23, 2024 | CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU- BRGY. POBLACION, BACLAYON RURAL PRIMARY HEALTH CENTER, BOHOL | On-Going | ₱14.9M |
| 24HA0147 | Sep 13, 2024 | REHABILITATION OF MULTI-PURPOSE FACILITY, BACLAYON, BOHOL (PHASE 1) | Completed | ₱24.7M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.