Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 21ID0053

DPWH infrastructure contract
Contract ID:
21ID0053
Fingerprint:
f7ff44e3c5b859…de981c9f94 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 15, 2021 (5 yrs 7 mo ago) · Target/actual end Aug 31, 2021
Description:
NETWORK DEVELOPMENT PROGRAM-ROAD WIDENING-PRIMARY ROADS-PALO-CARIGARA-ORMOC ROAD K0940+910-K0941+442
Category:
Roads
Implementing office:
DPWH Leyte 2nd DEO · Region VIII
Contractor:
UNIMASTERS CONGLOMERATION, INCORPORATED · DPWH contractor code 3390
Contract amount:
₱28,789,135.05 (₱28.8M)
Funding source:
Regular Infra - GAA 2021 OO-1
Budget year:
2021

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25ID0066Apr 14, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 1, JARO,LEYTECompleted₱5.9M
25ID0033Apr 7, 2025CONSTRUCTION OF ROAD,BARANGAY LA PAZ,JARO,LEYTEOn-Going₱14.5M
25ID0021Apr 4, 2025CONSTRUCTION OF ROAD,BARANGAY ANIBONGON, JARO,LEYTEOn-Going₱5.2M
25ID0034Apr 4, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY VILLA PAZ,JARO,LEYTECompleted₱7.9M
25ID0032Apr 3, 2025CONSTRUCTION OF ROAD, BARANGAY ATIPOLO,JARO,LEYTEOn-Going₱19.8M
25ID0012Mar 24, 2025CONSTRUCTION OF ROAD, SITIO SOLEDAD, BARANGAY SANTO NIÑO, JARO, LEYTECompleted₱9.9M
25ID0027Mar 20, 2025CONSTRUCTION OF ROAD,BARANGAY SAN ROQUE,JARO,LEYTECompleted₱16.0M
25ID0028Mar 20, 2025CONSTRUCTION OF ROAD,SITIO MAITOM,BARANGAY SAN AGUSTIN, JARO,LEYTEOn-Going₱9.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.