Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 21IG0076

DPWH infrastructure contract
Contract ID:
21IG0076
Fingerprint:
51e8f418ff6390…d78a45bf16 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 4, 2021 (5 yrs 8 mo ago) · Target/actual end Oct 29, 2021
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING,(BARANGAY COMATIN,BARANGAY SAN SOTERO,BARANGAY CARANHUG,BARANGAY BATUG,BARANGAY MALITBOGAY,BARANGAY BINULHO,BARANGAY ULHAY,BARANGAY RIZAL),JAVIER,LEYTE
Category:
Buildings and Facilities
Implementing office:
DPWH Leyte 5th DEO · Region VIII
Contractor:
BEEROCK ENTERPRISES INCORPORATED · DPWH contractor code 45481
Contract amount:
₱6,849,024.98 (₱6.8M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25IG0021Jun 3, 2025CONSTRUCTION OF ROAD, BARANGAY SAN SOTERO, JAVIER, LEYTECompleted₱4.9M
25IG0032May 20, 2025NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - JAVIER BY-PASS ROAD, LEYTECompleted₱19.6M
25IG0056May 20, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BINULHO, JAVIER, LEYTECompleted₱3.0M
25I00014Apr 10, 2025ASSET PRESERVATION - PREVENTIVE MAINTENANCE - PRIMARY ROADS - MAHARLIKA HIGHWAY - K0961+530 - K0961+673, LEYTE 5TH LDOn-Going₱8.5M
25I00023Apr 10, 2025ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS - MAHARLIKA HIGHWAY - K0963+902 - K0964+979, LEYTE 5TH LDOn-Going₱52.3M
25IG0011Mar 27, 2025NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ABUYOG BY-PASS ROAD, LEYTECompleted₱49.0M
25IG0002Mar 11, 2025CONSTRUCTION OF ROAD, BARANGAY ANDRES BONIFACIO, JAVIER, LEYTECompleted₱4.9M
25IG0015Mar 11, 2025CONSTRUCTION OF ROAD, BARANGAY PINOCAWAN, JAVIER, LEYTECompleted₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.