Project 21K00323

DPWH infrastructure contract
Contract ID:
21K00323
Fingerprint:
a2d7e973ab5ce0…c968a1c213 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Nov 26, 2021 (4 yrs 11 mo ago) · Target/actual end Mar 25, 2022
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING, BGRY. LUMBATAN PATAINGUD, BUADIPOSO-BUNTONG, LANAO DEL SUR
Category:
Buildings and Facilities
Implementing office:
DPWH Region X · Region X
Contractor:
AL - MUJIV CONSTRUCTION · DPWH contractor code 45154
As listed: AL-MUJIV CONSTRUCTION
Contract amount:
₱2,890,934.12 (₱2.9M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
18fa7fc59809…Nov 22, 2021DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION X₱2,890,934.12

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
23K00348Dec 27, 2023CONCRETING OF LUMBATAN-MANACAB ROAD, BUADIPUSO BUNTONG, LANAO DEL SURCompleted₱14.3M
22K00308Sep 30, 2022CONST./UPGRADING/REHAB. OF DRAIANGE ALONG NATIONAL ROADS-SECONDARY ROADS, MARAWI-MASIU RD - (S01603MN) CHAINAGE 8940 - CHAINAGE 9614.512,CHAINAGE 9730-CHAINAGE 10305Completed₱37.4M
22K00131Sep 22, 2022CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY MANACAB, BUADIPOSO BUNTONG, LANAO DEL SURCompleted₱5.7M
21K00291May 23, 2022CONSTRUCTION OF DRAINAGE OPEN CANAL, BRGY. BUAYAAN, DITSAAN-RAMAIN, LANAO DEL SURCompleted₱9.7M
21K00204May 28, 2021CONSTRUCTION OF MULTI-PURPOSE BUILDING (ABC HALL), BARANGAY MANACAB, BUADIPOSO-BUNTONG, LANAO DEL SURCompleted₱4.3M
20K00371Jan 15, 2021CONCRETING OF BRGY. SAPOT FMR, SAPOT, BUADIPOSO-BUNTONG, LANAO DEL SURCompleted₱11.5M
20K00381Jan 15, 2021CONCRETING OF BARANGAY MANACAB FMR, BRGY. MANACAB, BUADIPOSO-BUNTONG, LANAO DEL SURTerminated₱0
20K00384Jan 15, 2021CONSTRUCTION OF 1ST2CL, BUNTONG ES (POB ANNEX), BUADIPOSO-BUNTONG, LANAO DEL SURTerminated₱0

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.