Project 21MI0085
DPWH infrastructure contract
Contract ID:
21MI0085
Fingerprint:
588fba9ef6e5c8…e03b9e4a93 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 27, 2021 (5 yrs 5 mo ago) · Target/actual end Oct 26, 2021
Description:
CONSTRUCTION OF DISTRICT HOSPITAL BUILDING, BRGY. WADYA, BANISILAN, NORTH COTABATO
Category:
Buildings and Facilities
Implementing office:
DPWH Cotabato 3rd DEO · Region XII
Contractor:
BARRIST BUILDERS AND CONSTRUCTION SUPPLY · DPWH contractor code 39785
Contract amount:
₱9,892,438.03 (₱9.9M)
Funding source:
Regular Infra - GAA 2021 LP
Budget year:
2021
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| b0e9ac7ec342… | May 11, 2021 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAY COTABATO 3RD DEO | ₱9,892,438.03 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25MI0094 | Aug 19, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING (LEGISLATIVE BUILDING) IN BANISILAN, COTABATO | Completed | ₱4.7M |
| 25MI0095 | Aug 19, 2025 | COMPLETION/REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) IN BRGY. MIGUEL MACASARTE, BANISILAN, COTABATO | Completed | ₱5.6M |
| 25MI0096 | Aug 19, 2025 | COMPLETION/REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) IN BRGY. TINIMBACAN, BANISILAN, COTABATO | Completed | ₱4.7M |
| 25MI0097 | Aug 19, 2025 | COMPLETION/REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) IN BRGY. KALAWAIG, BANISILAN, COTABATO | Completed | ₱4.6M |
| 25MI0086 | Jul 29, 2025 | CONSTRUCTION OF ROAD, BRGY. MALINAO, BANISILAN, COTABATO | Completed | ₱6.6M |
| 25MI0088 | Jul 29, 2025 | CONSTRUCTION OF ROAD AT SITIO RANCHO BRGY. WADYA, BANISILAN, COTABATO | Completed | ₱6.6M |
| 25M00175 | Jul 7, 2025 | ROAD WIDENING - BANISILAN-GUILING-ALAMADA-LIBUNGAN RD - K1642+1149 - K1645+057, BANISILAN, NORTH COTABATO | On-Going | ₱125.3M |
| 25MI0021 | May 23, 2025 | CONSTRUCTION OF ROAD, BARANGAY PINAMULAAN, BANISILAN, NORTH COTABATO | Completed | ₱9.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.