Project 21OC0049
DPWH infrastructure contract
Contract ID:
21OC0049
Fingerprint:
9fef06bf326d0d…6ba1cb07de Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 22, 2022 (4 yrs 7 mo ago) · Target/actual end Jan 4, 2023
Description:
CONSTRUCTION OF REVETMENT WALL AT BARANGAY RIZAL PUMPING STATION (DOWNSTREAM PORTION), BRGY. RIZAL,MAKATI CITY, METRO MANILA
Category:
Flood Control and Drainage
Implementing office:
DPWH Metro Manila 2nd DEO · National Capital Region
Contractor:
C.B. TAMPENGCO CONSTRUCTION & SUPPLY · DPWH contractor code 18505
Contract amount:
₱21,412,893.00 (₱21.4M)
Funding source:
Regular Infra - GAA 2021 OO-2
Budget year:
2021
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| a88dbd85fe1c… | Mar 21, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - METRO MANILA 2ND D | ₱21,412,893.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25OB0443 | Jul 13, 2026 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. NEW LOWER BICUTAN, TAGUIG CITY (PHASE 1) | On-Going | ₱46.9M |
| 25OB0367 | Apr 15, 2026 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING AND SITE DEVELOPMENT AT LAKESHORE AT BARANGAY LOWER BICUTAN, TAGUIG CITY | On-Going | ₱47.0M |
| 25OB0409 | Aug 14, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, NRCPO, CAMP BAGONG DIWA, TAGUIG CITY | On-Going | ₱29.1M |
| 25OB0437 | Aug 14, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, SPD COMPOUND, LAWTON AVE., BARANGAY WESTERN BICUTAN, TAGUIG CITY (PHASE 1) | On-Going | ₱48.5M |
| 25OC0178 | Jul 8, 2025 | REHABILITATION/IMPROVEMENT OF SOUTH SUPER H-WAY WEST SERVICE RD (S03387LZ)(INTERMITTENT) PARAÑAQUE CITY, METRO MANILA | Completed | ₱12.8M |
| 25OB0371 | Jun 27, 2025 | CONSTRUCTION OF MULTI-PURPOSE FACILITIES AT LAKESHORE, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 1) | On-Going | ₱48.5M |
| 25OB0372 | Jun 27, 2025 | CONSTRUCTION OF MULTI-PURPOSE FACILITIES AT LAKESHORE, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 2) | On-Going | ₱48.5M |
| 25OB0373 | Jun 27, 2025 | CONSTRUCTION OF MULTI-PURPOSE FACILITIES AT LAKESHORE, BARANGAY LOWER BICUTAN, TAGUIG CITY (PHASE 5) | On-Going | ₱72.7M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.