Project 22AC0070
DPWH infrastructure contract
Contract ID:
22AC0070
Fingerprint:
0b45ed5a9b5824…ac80dc89ae Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 7, 2022 (4 yrs 7 mo ago) · Target/actual end Jan 12, 2023
Description:
CONCRETING OF BRGY. PAING FMR, BRGY. PAING, BANTAY, ILOCOS SUR
Category:
GAA 2022 DA FMR
Implementing office:
DPWH Ilocos Sur 1st DEO · Region I
Contractor:
Contract amount:
₱29,850,000.00 (₱29.9M)
Funding source:
Outside Infra - GAA 2022 DA FMR
Budget year:
2022
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25AC0091 | Jul 13, 2026 | CONSTRUCTION OF CLASSROOMS, BANTAY WEST IS, BANTAY, ILOCOS SUR | On-Going | ₱12.2M |
| 25AC0073 | Jun 15, 2026 | CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING (TOURIST CENTER), BANTAY, ILOCOS SUR | On-Going | ₱144.2M |
| 25AC0033 | Jul 11, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ABRA RIVER, BANTAY, ILOCOS SUR | Completed | ₱47.5M |
| 25AC0077 | Jul 10, 2025 | PREVENTIVE MAINTENANCE - PRIMARY ROADS MANILA NORTH RD - K0397+205 - K0398+925 | On-Going | ₱46.8M |
| 25AC0029 | Jun 27, 2025 | RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES, PAING BR. 2 (B04627LZ) ALONG MANILA NORTH RD | Completed | ₱8.4M |
| 25AC0038 | Jun 5, 2025 | CONSTRUCTION OF ROAD, BARANGAY SAGPAT, BANTAY, ILOCOS SUR | Completed | ₱5.8M |
| 25AC0064 | Jun 2, 2025 | CONSTRUCTION OF ROAD, BARANGAY TAGUIPORO TO BARANGAY RAOIS, BANTAY, ILOCOS SUR | On-Going | ₱19.2M |
| 25AC0006 | Apr 11, 2025 | CONSTRUCTION OF SPUR DIKE AT BANAOANG PIS, BANTAY, ILOCOS SUR | Completed | ₱14.1M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.