Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 22CC0311

DPWH infrastructure contract
Contract ID:
22CC0311
Fingerprint:
f6f6078316d3cb…43a4416ad8 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 4, 2022 (4 yrs 7 mo ago) · Target/actual end Oct 10, 2022
Description:
SPECIAL ROAD FUND - MOTOR VEHICLE USER'S CHARGE (MVUC) AS PER R.A. 11239 - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - MANILA NORTH ROAD (LZ) K0028+500 - K0029+000, K0029+200 - K0029+700, BOCAUE AND BALAGTAS, BULACAN
Category:
Roads
Implementing office:
DPWH Bulacan 1st DEO · Region III
Contractor:
G.D.L. CONSTRUCTION · DPWH contractor code 22796
Contract amount:
₱84,859,619.45 (₱84.9M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25C00499Jun 16, 2025BRIDGE PROGRAM-RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES-UGONG BRIDGE (BO1987LZ) ALONG MANILA NORTH ROAD, PROVINCE OF BULACANCompleted₱16.2M
25CC0385May 23, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (TRAINING CENTER), HAGONOY, BULACANOn-Going₱19.3M
25CC0406May 23, 2025REHABILITATION OF UGONG CREEK (LEFT SIDE) BALAGTAS, BULACAN (PACKAGE G)On-Going₱95.0M
25CC0490May 23, 2025CONSTRUCTION OF REINFORCED CONCRETE RIVER PROTECTION ALONG BALAGTAS RIVER, BARANGAY SAN JUAN, PUROK 1, BALAGTAS, BULACAN (PACKAGE D)On-Going₱95.0M
25C00473Apr 8, 2025ASSET PRESERVATION PROGRAM-REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS-PRIMARY ROADS-MANILA NORTH ROAD, PROVINCE OF BULACANOn-Going₱135.1M
25CC0433Apr 8, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, PLAZA BIGAA, BARANGAY BOROL 1ST, BALAGTAS, BULACANOn-Going₱14.5M
25CC0200Mar 21, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY HALL, BARANGAY BOROL 2ND, BALAGTAS, BULACANOn-Going₱4.9M
25CC0236Mar 21, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY SAN JUAN, BALAGTAS, BULACANOn-Going₱14.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.