Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 22CK0073

DPWH infrastructure contract
Contract ID:
22CK0073
Fingerprint:
3ea08bc0b76468…e274695860 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 24, 2022 (4 yrs 7 mo ago) · Target/actual end May 8, 2023
Description:
ASSET PRESERVATION PROGRAM: CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG TARLAC - ZAMBALES ROAD, CAPAS, TARLAC
Category:
Roads
Implementing office:
DPWH Tarlac 2nd DEO · Region III
Contractor:
Contract amount:
₱29,385,507.17 (₱29.4M)
Funding source:
Regular Infra - GAA 2022 OO-1
Budget year:
2022

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26CK0011Jun 26, 2026ASSET PRESERVATION PROGRAM: PREVENTIVE MAINTENANCE - TERTIARY ROADS ALONG TARLAC - ZAMBALES NORTH WEST DIVERSION ROAD, K0111 + (-312) - K0111 + 790, CAPAS, TARLACOn-Going₱19.8M
25CK0093May 20, 2025REHABILITATION OF EARTH SLOPE DIKE, UPSTREAM OF BANGOT BRIDGE - BANGUT RIVER LEFT SIDE (SEGMENT A), CAPAS, TARLACCompleted₱96.5M
25CK0094May 20, 2025REHABILITATION OF EARTH SLOPE DIKE, UPSTREAM OF BANGOT BRIDGE - BANGUT RIVER LEFT SIDE (SEGMENT B), CAPAS, TARLACCompleted₱96.5M
25CK0095May 20, 2025REHABILITATION OF EARTH SLOPE DIKE, UPSTREAM OF BANGOT BRIDGE - BANGUT RIVER LEFT SIDE (SEGMENT C), CAPAS, TARLACCompleted₱96.5M
25CK0102May 20, 2025REHABILITATION OF EARTH SLOPE DIKE, UPSTREAM OF BANGOT BRIDGE - BANGUT RIVER LEFT SIDE (SEGMENT D), CAPAS, TARLACCompleted₱96.5M
25CK0103May 20, 2025REHABILITATION OF EARTH SLOPE DIKE, UPSTREAM OF BANGOT BRIDGE - BANGUT RIVER LEFT SIDE (SEGMENT E), CAPAS, TARLACCompleted₱96.5M
25CK0104May 20, 2025REHABILITATION OF EARTH SLOPE DIKE, UPSTREAM OF BANGOT BRIDGE - BANGUT RIVER RIGHT SIDE (SEGMENT A), CAPAS, TARLACCompleted₱96.5M
25CK0105May 20, 2025REHABILITATION OF EARTH SLOPE DIKE, UPSTREAM OF BANGOT BRIDGE - BANGUT RIVER RIGHT SIDE (SEGMENT B), CAPAS, TARLACOn-Going₱96.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.