Project 22DD0281
DPWH infrastructure contract
Contract ID:
22DD0281
Fingerprint:
2e8c25977a8160…6d0b9a8dba Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 29, 2022 (4 yrs 7 mo ago) · Target/actual end Oct 27, 2022
Description:
CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF PAYAPA-BUKAL BRIDGE INCLUDING APPROACHES, PADRE GAR
Category:
Bridges
Implementing office:
DPWH Batangas 4th DEO · Region IV-A
Contractor:
M.G. SALAZAR CONSTRUCTION CORP. (FOR. M.G. SALAZAR · DPWH contractor code 4072
Contract amount:
₱57,620,787.00 (₱57.6M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 24DD0305 | Mar 27, 2025 | CONCRETING OF BARANGAY PANSOL FMR, BARANGAY PANSOL, PADRE GARCIA, BATANGAS | On-Going | ₱14.5M |
| 24DD0311 | Mar 27, 2025 | CONCRETING OF BARANGAY SAN FELIPE FMR, BARANGAY SAN FELIPE, PADRE GARCIA, BATANGAS | On-Going | ₱14.9M |
| 24DD0312 | Mar 27, 2025 | CONCRETING OF BARANGAY BAWI FMR, BARANGAY BAWI, PADRE GARCIA, BATANGAS | On-Going | ₱14.5M |
| 25DD0357 | Mar 27, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUTURE PROGRAM (BIP), PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION (COMPLETION) OF WATER SUPPLY SYSTEM, BARANGAY CASTILLO, PADRE GARCIA, BATANGAS | On-Going | ₱2.9M |
| 25DD0101 | Mar 18, 2025 | ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, PREVENTIVE MAINTENANCE - SECONDARY ROADS, LIPA-ROSARIO RD - K0086 + 685 - K0087 + 373, K0088 + 398 - K0088 + 858 | On-Going | ₱38.2M |
| 25DD0103 | Mar 18, 2025 | ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, BATANGAS-QUEZON RD - K0115 + 587 - K0116 + 000, K0121 + 719 - K0121 + | On-Going | ₱28.5M |
| 25DD0015 | Feb 21, 2025 | ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG TUBIG NG BAYAN RIVER, P | On-Going | ₱56.2M |
| 25DD0031 | Feb 21, 2025 | ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG TUBIG NG BAYAN RIVER, B | On-Going | ₱56.2M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.