Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 22DH0084

DPWH infrastructure contract
Contract ID:
22DH0084
Fingerprint:
70d7d1e82fa7a5…3cddb27e8f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 6, 2022 (3 yrs 11 mo ago) · Target/actual end Dec 20, 2022
Description:
CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SETAGE AND SEWERAGE/RAIN WATER COLLECTORS - RAIN WATER COLLECTOR SYSTEM (11 UNITS)
Category:
Water Provision and Storage
Implementing office:
DPWH Laguna 1st DEO · Region IV-A
Contract amount:
₱4,394,610.00 (₱4.4M)
Funding source:
Regular Infra - GAA 2021 CSSP
Budget year:
2021

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25DH0041May 15, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY PAAGAHAN, MABITAC, LAGUNACompleted₱4.8M
25DH0015Feb 11, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE (TUNGKOD RIVER), PAAGAHAN CIS, MABITAC, LAGUNACompleted₱14.3M
24DH0008Oct 1, 2024REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE, SECONDARY ROADS RIZAL BDRY-FAMY-QUEZON RD K0067+(-340)-K0067+(-280), RIZAL BDRY-FAMY-QUEZON RDCompleted₱32.0M
24DH0078Sep 5, 2024CONSTRUCTION OF ROAD WITH OPEN CANAL IN BRGY. DAMBO, PANGIL, LAGUNACompleted₱8.8M
24DH0065Jul 25, 2024CONCRETING OF BRGY. MATALATALA FMR, BRGY. MATALATALA, MABITAC, LAGUNACompleted₱9.9M
24D00091May 21, 2024CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG LAGUNA LAKESHORE AT BARANGAY PAG-ASA, PHASE II, MABITAC, LAGUNACompleted₱96.5M
24DH0038May 7, 2024CONSTRUCTION OF MULTI PURPOSE BUILDING, BARANGAY NANGUMA, MABITAC, LAGUNACompleted₱4.9M
24DH0006Feb 20, 2024PREVENTIVE MAINTENANCE-SECONDARY ROADS RIZAL BDRY-FAMY-QUEZON RD K0074+659-K0075+200, MABITAC, LAGUNACompleted₱28.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.