Physical progress:
100%
Timeline:
Start May 23, 2022 (4 yrs 5 mo ago) · Target/actual end Sep 21, 2022
Description:
ROAD WIDENING ALONG CALAPAN SOUTH ROAD K0062+649 - K0062+926.50, SOCORRO, ORIENTAL MINDORO
Category:
GAA 2022 OO-1
Implementing office:
DPWH Mindoro Oriental DEO · MIMAROPA Region
Contractor:
JARO BUILDERS & CONSTRUCTION SUPPLY · DPWH contractor code 25560
Contract amount:
₱8,959,384.74 (₱9.0M)
Funding source:
Regular Infra - GAA 2022 OO-1
Budget year:
2022
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| c27d48b96ec1… | May 10, 2022 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - MINDORO ORIENTAL D | ₱8,959,384.74 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26EI0052 | Aug 25, 2026 | CONSTRUCTION / UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - CALAPAN SOUTH RD - K0071+ 766 - K0072 + 178, K0072 + 191 - K0074 + 252, K0074 + 550 - K0075 + 252, K0075 + 318 - K0075 + 949, PINAMALAYAN - GLORIA, ORIENTAL | On-Going | ₱103.4M |
| 25EI0162 | Jul 18, 2025 | CONSTRUCTION OF ORIENTAL MINDORO CENTRAL DISTRICT HOSPITAL, PINAMALAYAN, ORIENTAL MINDORO | Terminated | ₱0 |
| 25EI0164 | Jun 16, 2025 | COMPLETION (CONSTRUCTION) OF MULTI-PURPOSE BUILDING AT BRGY. ANOLING, PINAMALAYAN, ORIENTAL MINDORO, PHASE II | Completed | ₱2.9M |
| 25EI0165 | Jun 16, 2025 | COMPLETION (CONSTRUCTION) OF MULTI-PURPOSE BUILDING AT BRGY. PALAYAN, PINAMALAYAN, ORIENTAL MINDORO PHASE II | Completed | ₱2.9M |
| 25ED0129 | May 16, 2025 | RETROFITTING/STRENGTHENING OF PULA BRIDGE, PULA, SOCORRO, ORIENTAL MINDORO | Completed | ₱43.6M |
| 25EI0143 | Apr 8, 2025 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-CONSTRUCTION OF ROAD, MARAYOS-SABANG, PINAMALAYAN, ORIENTAL MINDORO | On-Going | ₱14.5M |
| 25E00122 | Apr 6, 2025 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS TO AUGMENT RESILIENCY OF COASTYAL COMMUNITIES- CONST. OF COASTAL ROAD/SHORE PROTECTION ALONG BRGY. ZONE III-BRGY. QUINABIGAN, PINAMALAYAN, OR. MINDORO | On-Going | ₱231.0M |
| 25E00123 | Apr 6, 2025 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)- COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES- CONST. OF COASTAL ROAD/SHORE PROTECTION ALONG BRGY. ZONE III, STA. 000+290-STA. 000+620; STA. 000+660-STA. 000+813.50, PINAMALAYAN, O | On-Going | ₱230.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.