Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 22EH0022

DPWH infrastructure contract
Contract ID:
22EH0022
Fingerprint:
05e4d9abb31ffd…0174204a04 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 13, 2022 (4 yrs 6 mo ago) · Target/actual end Oct 10, 2022
Description:
CONSTRUCTION/REHABILITATION OF DULANGAN FLOOD MITIGATING STRUCTURE (DOWNSTREAM) ALONG DULANGAN RIVER CONTROL, STA. 07+120 - 07+305.82 (LS), STA. 07+060 - 07+116.87 (RS), STA. 07+120 - 07+164.52 (RS), MAGDIWANG, ROMBLON
Category:
GAA 2022 OO-2
Implementing office:
DPWH Romblon DEO · MIMAROPA Region
Contractor:
R.G. FLORENTINO CONST. & TRADING INC. · DPWH contractor code 18301
Contract amount:
₱45,829,108.83 (₱45.8M)
Funding source:
Regular Infra - GAA 2022 OO-2
Budget year:
2022

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25EH0102Jul 10, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BARANGAY SILUM, MAGDIWANG, ROMBLONOn-Going₱93.1M
25EH0159May 27, 2025CONSTRUCTION OF ROAD, BARANGAY TAMPAYAN LEADING TO SITIO SUONG ROAD, MAGDIWANG, ROMBLONOn-Going₱121.5M
25EH0105May 23, 2025CONSTRUCTION OF PROMENADE SEAWALL/ CAUSEWAY ALONG POBLACION TO AMBULONG, MAGDIWANG, ROMBLONOn-Going₱95.7M
25EH0041May 22, 2025CONSTRUCTION OF SEAWALL ALONG POBLACION LEADING TO AMBULONG, PHASE 2, MAGDIWANG, ROMBLONOn-Going₱71.3M
25EH0032Apr 11, 2025CONSTRUCTION OF JAO-ASAN FLOOD CONTROL STRUCTURE, PHASE 2, BARANGAY JAO-ASAN, MAGDIWANG, ROMBLONOn-Going₱48.0M
25EH0015Mar 27, 2025CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG SIBUYAN CIRCUMFERENTIAL ROADS, K0053+000 - K0053+212.57, K0059+746.03 - K0059+970 AS PER ACTUAL & RBIA, SIBUYAN ISLAND, ROMBLONCompleted₱4.8M
24EH0167Jan 13, 2025CONSTRUCTION OF IPIL MAGDIWANG FLOOD CONTROL STRUCTURE ALONG IPIL RIVER, MAGDIWANG, ROMBLONCompleted₱57.9M
24EH0068Jun 7, 2024CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG SIBUYAN CIRCUMFERENTIAL ROAD, K0047+134.13 - K0047+856.55 R/S (ACTUAL), K0047+144.13 - K0047+866.55 R/S (RBIA), SIBUYAN ISLAND, ROMBLONCompleted₱15.4M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.