Completed
Physical progress:
100%
Timeline:
Start Mar 21, 2022 (4 yrs 7 mo ago) · Target/actual end Jul 25, 2022
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY GUI-OB, ALCANTARA, ROMBLON
Category:
GAA 2022 CSSP
Implementing office:
DPWH Romblon DEO · MIMAROPA Region
Contractor:
MARCPHIL CONSTRUCTION OPC · DPWH contractor code 10949
As listed: MARCPHIL CONSTRUCTION OPC (FORMERLY: MARCPHIL CONSTRUCTION)
Location:
Contract amount:
₱4,907,970.59 (₱4.9M)
Funding source:
Regular Infra - GAA 2022 CSSP
Budget year:
2022
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25EH0154 | May 27, 2025 | CONSTRUCTION OF ROAD, BARANGAY LAWAN TO BARANGAY SAN ISIDRO (PHASE 2), ALCANTARA, ROMBLON | On-Going | ₱93.5M |
| 25EH0161 | May 27, 2025 | CONSTRUCTION OF ROAD, SITIO MAGSUPOT TO SITIO ILAYA, BARANGAY CALAGONSAO, ALCANTARA, ROMBLON | On-Going | ₱140.2M |
| 25EH0116 | May 23, 2025 | CONSTRUCTION OF CAMILI- RNIT ACCESS ROAD, ALCANTARA, ROMBLON | On-Going | ₱11.6M |
| 25EH0088 | May 21, 2025 | CONSTRUCTION OF ROAD, ALCANTARA TO ODIONGAN, ALCANTARA, ROMBLON | On-Going | ₱142.7M |
| 25EH0003 | Mar 28, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), ALCANTARA NATIONAL HIGH SCHOOL, ALCANTARA, ROMBLON | Completed | ₱4.9M |
| 25EH0006 | Mar 24, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), ROMBLON NATIONAL INSTITUTE OF TECHNOLOGY - RNIT, PHASE I, BARANGAY POBLACION, ALCANTARA, ROMBLON | Completed | ₱5.9M |
| 25EH0037 | Mar 24, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), ALCANTARA NATIONAL HIGH SCHOOL, SENIOR HIGH SCHOOL, ALCANTARA, ROMBLON | Completed | ₱4.9M |
| 25E00141 | Mar 12, 2025 | ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC P[UBLIC BUILDINGS/FACILITIES- CONST. OF COASTAL ROAD, BRGY. CALAGONSAO, ALCANTARA, ROMBLON | On-Going | ₱276.2M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.