Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 22FF0083

DPWH infrastructure contract
Contract ID:
22FF0083
Fingerprint:
b443d02a52c747…31b37ac2db Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jan 16, 2023 (3 yrs 9 mo ago) · Target/actual end Apr 15, 2023
Description:
CONST. OF ONE(1) STOREY TWO(2) CLASSROOM SCHOOL BUILDING(UNDER DEPED CY 2022 BEFF BATCH 2), STO DOMINGO ELEMENTARY SCHOOL BOMBON CAMARINES SUR
Category:
Buildings and Facilities
Implementing office:
Contractor:
MEGA-ANT BUILDERS AND CONSTRUCTION SUPPLIES · DPWH contractor code 52876
Contract amount:
₱5,385,293.09 (₱5.4M)
Funding source:
Outside Infra - GAA 2022 DepEd BEFF
Budget year:
2022

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
f41c3db8ed3c…Dec 23, 2022DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAMARINES SUR 3RD₱5,348,000.00

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25FF0051Aug 28, 2025BIP;ACCESS ROADS &/OR BRIDGES FROM THE NATL. ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDING/FACILITIES-CONST. OF BRIDGES ,PAGAO BRIDGE,BARANGAY PAGAO BOMBON CAMARINES SUROn-Going₱29.2M
25FF0014Mar 26, 2025BIP;ACCESS ROAD &/OR BRIDGES FROM THE NATL. RD. LEADING TO MAJOR-STRATEGIC PUBLIC BLDG./FACILITIES-CONST. OF ROAD BRGY SIEMBRE,BOMBON CAMARINES SURCompleted₱4.9M
24FF0056May 9, 2024BIP;ACCESS ROADS & /OR BRIDGES FROM THE NATIONAL ROAD LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONST. OF ROAD BRGY. CARANGCANG MAGARAO-BRGY SAN FRANCISCO BOMBON CAMARINES SURCompleted₱4.8M
24FF0006Feb 22, 2024BIP;ACCESS ROADS & OR BRIDGES FROM THE NATL. ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES CONST OF ACCESS ROAD BRGY. SIEMBRE BOMBON CAMARINES SURCompleted₱4.8M
23FF0101Jan 9, 2024CONSTRUCTION OF 2 STY 4 CL (PHASE 1 )SAN ANTONIO ELEMENTARY SCHOOL UNDER CY 2023 BFF BATCH 1 NEW CONSTRUCTION, BOMBON CAMARINES SURCompleted₱15.3M
23FF0069Jul 10, 2023CONCRETING OF BRGY. SAN FRANCISCO BOMBON TO BRGY CARANGCANG MAGARAO FMR, BRGY SAN FRANCISCO BOMBON & BRGY. CARANGCANG MAGARAO CAMARINES SURCompleted₱9.7M
23FF0031Apr 24, 2023001;ENSURE SAFE & RELIABLE NATIONAL ROAD SYSTEM- ASSET PRESERVATION PROGRAM-PREVENTIVE MAINT. TERTIARY ROAD - NAGA CITY BDRY.- CALABANGA-BALONGAY ROAD KO443+686-KO445+035.30Completed₱48.5M
21FF0034Apr 6, 2022CONSTRUCTION OF MULTI PURPOSE BUILDING(COVERED COURT) BARANGAY SAN JOSE (BOMBON CENTRAL SCHOOL) BOMBON CAMARINES SURCompleted₱5.8M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.